100%專業的1z0-1057-25考試資訊,最好的考試資料幫助妳快速通過1z0-1057-25考試近來,Oracle的認證考試越來越受大家的歡迎。Oracle的認證資格也變得越來越重要。作為被 IT行業廣泛認可的考試,1z0-1057-25認證考試是Oracle中最重要的考試之一。取得了這個考試的認證資格,你就可以獲得很多的利益。如果你也想參加這個考試的話,VCESoft的1z0-1057-25考古題是你準備考試的時候不能缺少的工具。因为这是1z0-1057-25考试的最优秀的参考资料。 最新的 Project Financials Management Cloud 1z0-1057-25 免費考試真題 (Q42-Q47):問題 #42
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
A. 0
B. 1
C. 2
D. 3
答案:C
解題說明:
Budget 5,000Actuals 800Commitment 600
ETC = Budget - Actuals - Commitment
ETC = 5,000-800-600 = 3,600 Budget available for next 4 months = 3,600/4 = 900/month
問題 #43
Your organization has been using project class categories and codes for reporting purposes and is set up at the project level. You recently defined a new project type, Capital-Contract, and created new class categories named Build, Operate, and Transfer (BOT) and Build, Transfer, and Maintain (BTM), with class codes of Yes
/No. But on creation of a project, you are unable to associate these class categories and codes.
Identify two setups that are mandatory for these class categories and codes to be displayed. (Choose two.)
A. Class codes should be assigned to project unit.
B. Class codes should be associated with a related set code.
C. Class categories should be assigned to business unit.
D. Class categories should be assigned to project type.
答案:B,D
解題說明:
Ref: https://docs.oracle.com/en/cloud ... project-foundation- configuration-manage-project-types.html#OAPFM360164 Topic - Associating Project Types and Class Categories: Examples Project classifications group your projects according to categories and codes that you define. When you associate project classifications with project types, the classification is available for selection on projects with that project type.
Use any of the following methods to associate class categories with project types:
* Add a classification to the project type definition
For each classification that you associate with the project type, you can enable the Assign to All Projects option to automatically add the classification to the project definition for all new projects with the project type. When this option is enabled, all projects with this project type must be assigned a class code for the class category.
* Add a project type to the class category definition
* Enable the Assign to all Project Types option on the class category definition
問題 #44
Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.
What are three conditions for new employees to show up in the list? (Choose three.)
A. All new employees created as persons must be assigned to a department.
B. All new employees created as persons must have an active project role.
C. All new employees created as persons must have an active supervisor.
D. Current date is before the effective date of the resource, and you did not enable the "Include people with future-dated effective start dates" option during the search.
E. All new employees created as persons must have an active assignment.
答案:A,D,E
問題 #45
Green House Corporation has decided to enable the budgetary control feature for their projects. At which two levels will they be able to enter the amounts in the budget versions for these projects?
(Choose two.)
A. Expenditure Category
B. Top resource
C. Project
D. Task
E. Expenditure Type
答案:C,D
解題說明:
Budgetary control is a feature that allows you to monitor and control project costs against approved budgets.
You can enter the amounts in the budget versions for these projects at two levels: Task and Project. These levels correspond to the budgetary control levels that are defined for the project type. You can also view and compare the budget amounts and actual costs at these levels using reports and dashboards. Expenditure Type, Top Resource, and Expenditure Category are not levels at which you can enter the amounts in the budget versions for these projects. These are attributes that can be used to group and filter the budget and actual amounts for reporting purposes. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio- management/20c/oapfm/manage-project-budgets-and-forecasts.html#OAPFM2356191
問題 #46
Where is the Allow Override option for the Default Capitalized Interest Rate Schedule specified?
A. Manage Project Plan Type page
B. Manage Expenditure Type page
C. Manage Capitalized Interest Rates page
D. Manage Project Type page
E. Manage Capitalized Interest Rate Schedules page
答案:D
解題說明:
The Allow Override option for the Default Capitalized Interest Rate Schedule is specified on the Manage Project Type page. This option allows you to override the default capitalized interest rate schedule for a project or task that uses the project type. The default capitalized interest rate schedule is used to calculate the capitalized interest amount for a project or task based on the interest rates and dates defined in the schedule.
Reference: https://docs.oracle.com/en/cloud ... pfm/manage-project- costs.html#OAPFM2356031