| Topic | Weight |
| Duty A: Conducting Pre-Installation Activities | 20% |
| Task 1: Review Audiovisual Project Documentation | 4% |
| Task 2: Conduct Technical Site Survey | 4% |
| Task 3: Prepare for Audiovisual Installation | 4% |
| Task 4: Evaluate Overall Facility Readiness | 4% |
| Task 5: Conduct On-Site Preparations for Installation | 4% |
| Duty B: Conducting Site Rough-In/First-Fix | 10% |
| Task 1: Deinstallation of Existing Equipment and cabling | 2% |
| Task 2: Mount Substructure | 4% |
| Task 3: Pull Cable | 4% |
| Duty C: Installing Audiovisual Systems | 38% |
| Task 1: Assemble AV Rack | 4% |
| Task 2: Wire the AV Equipment Rack | 5% |
| Task 3: Distribute AV Equipment | 4% |
| Task 4: Mount AV Equipment | 4% |
| Task 5: Terminate Cables | 5% |
| Task 6: Configure Network Properties of Equipment | 4% |
| Task 7: Load Configuration and Control Programs | 4% |
| Task 8: Test the AV System | 4% |
| Task 9: Calibrate the AV System | 4% |
| Duty D: Perform Systems Close Out | 11% |
| Task 1: Demonstrate to Client or Client's Representative that System Performs to Specifications | 4% |
Task 2 rovide Training on System Operation | 4% |
| Task 3:Obtain Project Completion Sign Off from Client or Client's Representative | 3% |
| Duty E: Conducting Ongoing Project Responsibilities | 21% |
| Task 1: Complete Progress Reports | 3% |
| Task 2: Coordinate with Other Contractors | 4% |
| Task 3: Address Needed Field Modifications | 4% |
| Task 4: Repair AV Systems | 3% |