PSP資格関連題 & PSP関連問題資料PSP認定を取得することは、学生、教師、主婦など、さまざまな分野の多くの人々にますます一般的になっていることがわかっています。 全員がPSP認定を取得することが望まれます。 私たちのPSP試験ダンプ問題は、短時間で認定を取得するために最善を尽くすために非常に必要です。 PSP Exam Braindumpsは、試験に合格する手を差し伸べます。 PSP Exam Torrentは、認定を取得するための最良の学習ツールです。 ASIS Physical Security Professional Exam 認定 PSP 試験問題 (Q61-Q66):質問 # 61
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?
A. 03-21-04
B. 03-20-04
C. 02-19-04
D. 03-11-04
正解:D
解説:
* Original Completion Date (Normal Schedule):
* Project completion is originally set for 03-01-04 (based on all durations and dependencies).
* Slippage Details:
* Activity 1001: Slipped by 10 days.
* Activity 10002: Slipped by 35 days.
* Remaining activities retain original durations.
* Revised Completion Date Calculation:
* Adjust original completion date for the cumulative slippage of 35 days (largest impact).
* New completion date = 03-01-04 + 10 days = 03-11-04.
* Cross-Verification with Answer Options:
* Option A (02-19-04): Incorrect. Ignores slippage.
* Option B (03-21-04): Incorrect. Overestimates slippage impact.
* Option D (03-20-04): Incorrect. Does not align with the logical sequence.
* Option C (03-11-04): Correct. Matches adjusted completion date.
References:
* PSP Study Guide (2019), Section 2A - Schedule Development, Subsections on Forward and Backward Pass Calculations.
* AACE Recommended Practices, RP 10S-90.
質問 # 62
The long-term (more than 60 days) process of restoration activities after an emergency or disaster that returns the organization to its pre-event condition is called:
A. Business healing
B. Business resumption
C. Business recovery
D. Business continuity
正解:B
質問 # 63
At the end of month one, did the delay to the parking structure foundation delay the project?
A. Yes, by 4 calendar days.
B. Yes, by 14 calendar days.
C. Yes, by 9 calendar days.
D. NO.
正解:C
解説:
Scenario Review:
* Delay in the parking structure foundation is an off-critical path activity.
* No impact on the overall project completion date.
Delay Analysis:
* While the foundation activity is delayed, the float ensures that no downstream activities are impacted.
Cross-Verification:
* Option B: Incorrect. Assumes a 4-day impact.
* Option C: Incorrect. Overestimates delays.
* Option D: Incorrect. Miscalculates delays.
質問 # 64
During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?
A. Delay Manufacture Product by 5 days
B. Expedite Package Product by 5 days
C. Expedite Draft Product Manual by 5 days
D. Delay Release for Manufacture by 5 days
正解:C
解説:
To maintain the product availability date while accommodating a 15-day delay in proofing corrections, the best course of action is to expedite another activity on the critical path. The PSP Study Guide outlines methods for schedule recovery and acceleration (Section 2.3.5, "Acceleration"). Expediting the Draft Product Manual by 5 days helps redistribute the time lost, aligning subsequent tasks to achieve the original completion milestone without delaying the overall schedule.
質問 # 65
A good change management plan___________.
A. is detailed during the planning phase
B. tracks minor decisions
C. is provided to stakeholders after it is created
D. involves only the project controls team
正解:A
解説:
* Best Practices for Change Management Plans:
* Effective plans are developed in the planning phase, ensuring all stakeholders understand how changes will be managed.
* Evaluation of Options:
* Option A: Incorrect. Stakeholders are involved during development, not just after.
* Option C: Incorrect. A change management plan focuses on significant changes, not minor decisions.
* Option D: Incorrect. It involves all stakeholders, not just the project controls team.
* Option B: Correct. Change management plans are part of project planning.
References:
* PSP Study Guide (2019), Sections on Critical Path Analysis, Float Management, and Change Management.
* AACE Recommended Practices, RP 10S-90.