Project-Planning-Design試験の準備方法|権威のあるProject-Planning-Design日本語試験情報試験|ハイパスレートのARE 5.0 Project Planning & Design (PPD)模擬対策問題どのようにNCARB Project-Planning-Design試験に準備すると悩んでいますか。我々社のProject-Planning-Design問題集を参考した後、ほっとしました。弊社のProject-Planning-Designソフト版問題集はかねてより多くのIT事業をしている人々は順調にNCARB Project-Planning-Design資格認定を取得させます。試験にパースする原因は我々問題集の全面的で最新版です。 NCARB ARE 5.0 Project Planning & Design (PPD) 認定 Project-Planning-Design 試験問題 (Q55-Q60):質問 # 55
An elementary school requires a renovation, selective demolition, and a major addition in order to accommodate a growing student population. An architectural firm has prepared schematic design plans incorporating the school's increased programmatic needs, including an enlarged library, cafeteria, and gymnasium; a secure courtyard; and additional space for administrative offices and classrooms. The main entrance was relocated in order to improve the traffic and pedestrian flow at the beginning and end of the school day, and additional parking was provided to comply with current zoning requirements.
The existing single-story masonry building was built in 1950. Two small additions were built later: the north addition will be kept and repurposed, but the south addition will be demolished. The building contains asbestos and lead in roof soffits, floor tiles, pipe insulation, and window paint. All existing mechanical systems need to be replaced; new systems have not been selected.
Considerations for the renovation include:
*The relocated front entrance must be easily recognizable, highly visible, and secure.
*Interior and exterior materials need to be durable and maintainable in order to withstand frequent student abuse, but also economical due to strict budget limitations.
*Good indoor air quality and increased energy efficiency are priorities for the selection of mechanical equipment.
After completion, the entire school should look uniform, without a distinctive difference between the existing building and new addition.
Building information:
*Construction Type is II-B.
The following resources are available for your reference:
*Existing Plans, including site and floor plans
*Proposed Plans, including site and floor plans
*Cost Analysis
*Zoning Ordinance Excerpts, for off-street parking requirements
*IBC Excerpts, showing relevant code sections
*ADA Standards Excerpts, showing relevant sections from the ADA Standards for Accessible Design The project team decides to cover the roof area above the gymnasium and platform with 350 watt, stationary, photovoltaic (PV) panels. Each panel requires 20 square feet, accounting for access aisles and safety clearances. The PV system will be tied to the local power company's electrical grid, and will not have battery storage. The school is located in a region that gets an average of 4 usable hours of sunlight per day.
Which of the following PV system design considerations apply to this project? Check the three that apply.
Refer to the project involving an elementary school renovation and addition with photovoltaic (PV) panels on the gymnasium roof (350-watt panels, 20 sq ft each, ~4 usable sunlight hours/day). The PV system is grid-tied without battery storage.
Which of the following PV system design considerations apply? Check the three that apply.
A. The PV system will provide emergency power for the school if the grid goes down.
B. The gymnasium and platform structural system must be designed to support the load of the PV system.
C. The PV system will produce approximately 95.5 kW during peak sun conditions.
D. The PV panels should be mounted toward the student pick-up/drop-off.
E. The PV system will reduce the need for artificial lighting in the gymnasium and platform areas.
F. The PV system will be made up of approximately 273 panels.
正解:B、C、F
解説:
Comprehensive and Detailed Explanation From Exact Extract:
B: Structural support must accommodate PV panel weight and wind loads.
C: Number of panels is calculated by dividing total roof area by panel area (total panel count # 273).
F: Peak power output = number of panels × wattage per panel (273 × 350 W # 95.5 kW).
A: Grid-tied systems without batteries do not provide power during outages.
D: PV panels generate electricity but do not directly reduce artificial lighting needs.
E: Panels are mounted for optimal solar exposure, not necessarily toward pick-up areas.
References:
ARE 5.0 PPD - Environmental Conditions and Context, Solar Energy
The Architect's Handbook of Professional Practice, 15th Edition - Renewable Energy
質問 # 56
An owner requests full height, motorized solar shades for the lobby curtainwall.
Click on the area of the section detail where the shade should be installed so that it is concealed from the lobby. 正解:
解説:
Explanation:
The solar shade should be installed within the ceiling recess above the curtainwall, behind the horizontal soffit-specifically in the void space between the top of the curtainwall glazing and the structural ceiling soffit (the shaded area immediately above the curtainwall glass in the section).
質問 # 57
During design development of a new college laboratory facility, the owner asks the architect to include way- finding signage mounted adjacent to doors. The type of signage requested will project into the corridors of the building.
Which of the following should the architect consider when selecting the signage? Check the three that apply.
A. ADA accessibility requirements
B. Signage material and finish type
C. Local zoning ordinance on signage
D. Manufacturer installation information
E. IBC exit width requirements
F. International Energy Code
正解:A、D、E
解説:
Comprehensive and Detailed Explanation From Exact Extract:
When signage projects into corridors:
ADA requirements (A) ensure signage is accessible to all, including those with disabilities.
IBC exit width requirements (B) ensure projected signage does not reduce required egress widths.
Manufacturer installation information (F) guides proper, safe mounting and compliance with structural requirements.
Zoning (D) is generally for exterior signage.
Energy code (E) is not related.
Material and finish (C) affect aesthetics but not code compliance.
References:
ARE 5.0 PPD - Codes and Regulations, Accessibility
The Architect's Handbook of Professional Practice, 15th Edition - Signage Design
質問 # 58
A site has been engineered with a 1:20 grade.
Which of the following sidewalk designs would be the most cost-effective way to get from the top to the bottom and still be in compliance with the accessibility standards?
A. Cutting diagonally across the slope at 1:12 with no handrail
B. Cutting diagonally across the slope at 1:10 with a handrail
C. Switchback ramps at 1:12 with a handrail
D. At the same grade as the slope with no handrail
正解:A
解説:
Comprehensive and Detailed Explanation From Exact Extract:
A 1:20 slope means a 5% grade (1 vertical unit per 20 horizontal units), which is slightly steeper than the ideal maximum slope for accessible ramps.
* Option C: Cutting diagonally across the slope at 1:12 (~8.33%) slope without a handrail is the most cost-effective design that still complies with accessibility standards. According to the Americans with Disabilities Act (ADA) and ICC A117.1, the maximum slope for an accessible ramp is 1:12. Handrails are required on ramps with a rise greater than 6 inches (150 mm). If the rise is less than 6 inches, handrails are not required.
Because the diagonal cut reduces the slope to 1:12 and the total rise is likely less than 6 inches given the gentle 1:20 original slope, handrails are not mandatory, making this solution economical and code compliant.
* Option A: Switchback ramps at 1:12 with handrails are compliant but more expensive due to increased construction complexity and space requirements.
* Option B: A 1:10 slope (10%) exceeds the maximum allowed slope for accessible ramps and requires handrails, thus non-compliant.
* Option D: Following the existing 1:20 slope without modification does not provide the maximum accessibility slope and may be acceptable but might not comply with certain stricter local codes for ramps.
Therefore, Option C balances accessibility, cost, and compliance optimally.
References:
ARE 5.0 Project Planning & Design Content Outline: Environmental Conditions and Context - Site Accessibility and Grading ADA Standards for Accessible Design (2010) ICC A117.1 Accessibility Standards The Architect's Handbook of Professional Practice, 15th Edition, Chapter 7: Site Planning and Accessibility
質問 # 59
Examples of regulatory controls include which of the following elements? Check the four that apply.
A. Master plans
B. Economic models
C. Historic designation
D. Environmental management
E. Socio-political demographics
F. Fire protection
正解:A、C、D、F
解説:
Comprehensive and Detailed Explanation From Exact Extract:
Regulatory controls are governmental or authoritative rules that regulate land use, building design, and environmental protection.
Master plans (A): Provide regulatory frameworks guiding development.
Environmental management (B): Includes regulations on land, water, and air quality.
Fire protection (C): Enforced through codes and regulations.
Historic designation (E): Regulates preservation and alterations of historic sites.
Socio-political demographics (D) and economic models (F) are influential factors but are not regulatory controls.
References:
ARE 5.0 PPD - Codes and Regulations
The Architect's Handbook of Professional Practice, 15th Edition - Land Use Controls
________________________________________
P.S. JPNTestがGoogle Driveで共有している無料かつ新しいProject-Planning-Designダンプ:https://drive.google.com/open?id=157iCaBWSxlKIaocpxCVfw_5h60Ytfvx3 Author: seansto815 Time: yesterday 02:46
Wollen Sie größere Errungenschaften in der IT-Branche erzielen, dann ist es richtig, Pass4Test zu wählen. Die Schulungsunterlagen zur Oracle 1z0-1054-25 Zertifizierungsprüfung aus Pass4Test werden von den erfahrenen Experten durch ständige Praxis und Forschung bearbeitet. Sie verfügen über hohe Genauigkeiten und große Reichweite. Haben Sie die Schulungsunterlagen zur Oracle 1z0-1054-25 Zertifizierungsprüfung aus Pass4Test, dann haben Sie den Schlüssel zum Erfolg.
Welcome Firefly Open Source Community (https://bbs.t-firefly.com/)