PMP試験の準備方法|正確的なPMP資格模擬試験|信頼的なProject Management Professional (2025 Version)無料ダウンロード試験を怖く感じるのはかなり正常です。特にPMIのPMPのような難しい試験です。励ましだけであなたの試験への自信を高めるのは不可能だと知っていますから、我々は効果的なソフトを提供してあなたにPMIのPMP試験に合格させます。あなたはデモで我々のソフトの効果を体験することができます。あなたはデモから我々のPMIのPMPソフトを開発する意図とプロを感じることができます。 PMI Project Management Professional (2025 Version) 認定 PMP 試験問題 (Q1275-Q1280):質問 # 1275
Which of the following is NOT found in a project charter?
A. Procedures for managing changes to contracts
B. Assumptions that have been made about the project
C. The business case for the project
D. Constraints and limitations on the project work
正解:A
解説:
The procedure for managing changes to a contract is found in the contract management
plan. The other three answers - the business case, constraints and assumptions - are all things you typically find in a project charter.
質問 # 1276
During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice One of the client representatives, who is not a key decision maker, is extremely opinionated This client representative could become a roadblock to progress due to their perceived level of authority during meetings How should the project manager handle this moving forward?
A. Allocate time to gain buy-in from the stakeholder prior to key decision meetings.
B. Update the project schedule to cater to this particular stakeholder
C. Ask that only key decision makers attend the project meetings.
D. Update the risk register to consider the possible project impacts
正解:A
質問 # 1277
At the final project closeout meeting, the customer informs the project manager that they require only selected parts of the project information. What should the project manager do with the documentation internally?
A. Archive project documents per their own company's document retention policies.
B. Remove the unnecessary parts of the documentation to match the customer's request.
C. Comply with the current legislation for document retention.
D. Archive the entire documentation in the project management office (PMO) for retrieval upon customer request.
正解:A
解説:
Section: Closing
質問 # 1278
A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist from the team was average.
What should the project manager do to help the new compliance specialist improve?
A. Escalate this situation to the manager of the area for a possible solution
B. Contact the human resources (HR) manager about the team's feedback
C. Coordinate a one-to-one meeting with the specialist to assess the situation
D. Provide time for the specialist to adjust to the pace of the project
正解:C
質問 # 1279
A project is in the later stages of execution. The project engineer insists in every meeting that they were never consulted or informed of the project deliverables. However, the project manager communicated adequately and has the project engineer's approvals on record.
What should the project manager do?
A. Introduce the item in the next meeting, reminding all stakeholders of the project objectives.
B. Write a formal letter to human resources (HR) detailing the project engineer's unprofessional behavior.
C. Approach the project engineer's supervisor about possibly replacing the project engineer.
D. Engage the project engineer in a discussion to understand the concern and agree on a way forward.