Title: 100% Pass AACE-PSP Marvelous Latest Planning & Scheduling Professional (PSP) [Print This Page] Author: tedcook899 Time: yesterday 15:20 Title: 100% Pass AACE-PSP Marvelous Latest Planning & Scheduling Professional (PSP) 2026 Latest DumpsActual AACE-PSP PDF Dumps and AACE-PSP Exam Engine Free Share: https://drive.google.com/open?id=18GaTMY6J-x3ncNAiC106NYMcwRCGDKJZ
In addition to the AACE International AACE-PSP PDF questions, we offer desktop Planning & Scheduling Professional (PSP) Exam (AACE-PSP) practice exam software and web-based Planning & Scheduling Professional (PSP) Exam (AACE-PSP) practice test to help applicants prepare successfully for the actual Building Planning & Scheduling Professional (PSP) Exam (AACE-PSP) exam. These Planning & Scheduling Professional (PSP) Exam (AACE-PSP) practice exams simulate the actual AACE-PSP exam conditions and provide an accurate assessment of test preparation.
The AACE-PSP certification focuses on assessing the candidate's knowledge and skills in the field of project planning and scheduling. AACE-PSP exam covers a wide range of topics, including project planning, scheduling, resource management, and earned value management. AACE-PSP Exam is designed to test the candidate's ability to apply planning and scheduling principles and techniques to real-world projects.
AACE International AACE-PSP 100% Correct Answers - AACE-PSP Test FreeWould you like to attend AACE International AACE-PSP certification exam? Certainly a lot of people around you attend this exam. AACE International AACE-PSP test is an important certification exam. If you obtain AACE-PSP certificate, you can get a lot of benefits. Then you pick other people's brain how to put through the test. There are several possibilities to get ready for AACE-PSP test, but using good tools is the most effective method. Well, what is the good tool? Of course, DumpsActual AACE International AACE-PSP exam dumps are the best tool.
The AACE-PSP Certification Exam is designed for professionals who are involved in planning and scheduling projects. AACE-PSP exam tests the knowledge and skills of candidates in areas such as project planning, scheduling, cost management, risk management, and communication. Planning & Scheduling Professional (PSP) Exam certification is recognized globally and is highly respected by employers in the project management industry. It is ideal for individuals who want to advance their careers in project management or planning and scheduling. AACE International Planning & Scheduling Professional (PSP) Exam Sample Questions (Q111-Q116):NEW QUESTION # 111
What problems can a soils engineer deal with on a project?
A. Toxic soils.
B. Archeological findings.
C. Hidden subsurface conditions.
D. Survey error.
Answer: C
Explanation:
* Role of Soils Engineer:
Soils engineers address subsurface conditions, such as soil stability, unexpected geology, and underground obstacles.
* Evaluation of Other Options:
A: Survey errors are typically addressed by surveyors.
C: Archeological findings involve specialists in historical preservation.
D: Toxic soils are typically handled by environmental engineers.
* Verification with PSP Guidelines:
The PSP Study Guide includes subsurface investigations as a key responsibility for geotechnical professionals (Ref: PSP Study Guide, Chapter 1A: Site Conditions).
NEW QUESTION # 112
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:
A. Predecessor is activity 5001, successor is activity 8001
B. Predecessor is activity 9001, successor is activity 9002
C. Predecessor is activity 4001, successor is activity 8001
D. Predecessor is activity 5001, successor is activity 8002
Answer: A
Explanation:
* Definition of a Summary Activity (Hammock):
A summary activity, also referred to as a hammock activity, spans multiple detailed tasks and is governed by the earliest start (ES) of the first task and the latest finish (LF) of the last task.
* Activities 6001 through 6003 Overview:
6001: Starts after 5001 (Drill and Grout Dam Site).
6003: Ends before 8001 (Rock Fill to elevation 50).
* Identifying Predecessor and Successor:
Predecessor: Activity 5001 (Drill and Grout Dam Site).
Successor: Activity 8001 (Rock Fill to elevation 50).
* Cross-Verification:
Logical and temporal dependencies confirm that Activity 5001 must precede the hammock, and Activity 8001 must succeed it (Ref: PSP Study Guide, Chapter 2A: Logical Sequencing and Activity Relationships
NEW QUESTION # 113
The BEST reason to use multiple calendars is to:
A. evaluate float for the benefit of the contractor
B. more accurately show how the project will be built
C. track owner activities according to their specific calendar in order to develop a good working relationship
D. allow each specialty contractor to have a unique schedule of work/non-work periods
Answer: B
NEW QUESTION # 114
An earned value-based project control system can use either of which two budgets as the basis of its calculations?
A. Earned or budgeted cost yearly.
B. Linear feet or dollars.
C. Direct or indirect cost.
D. Labor hours or dollars.
Answer: A
NEW QUESTION # 115
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?
A. Assigned party responsibility for each work task
B. Tabular listing of activities showing duration, calendar ID, early and late dates
C. Detailed listing of working days for each calendar used
D. Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID