AACE-PSP入門知識、AACE-PSP過去問有効なAACE-PSP研究急流がなければ、あなたの利益はあなたの努力に比例しないといつも感じていますか?あなたは常に先延ばしに苦しみ、散発的な時間を十分に活用できないと感じていますか?答えが完全に「はい」の場合は、AACE-PSPの高品質で効率的なテストツールであるAACE-PSPトレーニング資料を試してみることをお勧めします。 AACE-PSP試験に合格し、夢のある認定資格を取得することで、あなたの成功は100%保証され、より高い収入やより良い企業へのより多くの機会を得ることができます。 AACE International Planning & Scheduling Professional (PSP) Exam 認定 AACE-PSP 試験問題 (Q135-Q140):質問 # 135
If all other work proceeds according to the Baseline plan, how many times will the critical path change?
A. 1.
B. 2.
C. Does not change.
D. 3.
正解:C
質問 # 136
For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?
A. Additional extended overhead is also being shown in this activity
B. Some costs resulting from the crashed efforts were forgotten in previous activities
C. Generally, more equipment is used for a crashed project; therefore, it costs more to demobilize
D. Management bonuses for early completion were included in this activity
正解:C
質問 # 137
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
A. 15 days.
B. 5 days.
C. 0 days.
D. 10 days.
正解:B
質問 # 138
Determine the correct formula and date for the late finish for Activity 2002.
A. LS.2003 - 1 day -> 10-06-01.
B. LS.2003 - 1 day -> 11.06.01.
C. LS.2003 + 1 day -> 10-07-01.
D. LS.2003 - 1 day -> 10-05-01.
正解:D
解説:
* Activity Relationships:
Activity 2002 is directly succeeded by Activity 2003 in the schedule.
The late start (LS) of Activity 2003 determines the late finish (LF) of Activity 2002, adjusted by any lags or additional constraints.
* Late Finish Calculation Formula:
LF of 2002 = LS of 2003 - 1 day.
This accounts for the predecessor-successor logic and the sequence of activities.
* Date Calculation:
Late start of 2003 = 10-06-01.
Late finish of 2002 = 10-06-01 - 1 day = 10-05-01.
* Verification:
PSP guidelines emphasize that late finish values are derived by subtracting any relevant time constraints from the successor's late start (Ref: PSP Study Guide, Chapter 2A: Backward Pass Calculations)
質問 # 139
Why does activity 1001 have two successor activities?
A. Because the problem could not effectively work with only one successor
B. Because there are two defined logic paths for the work
C. Because the duration of activities 2001, 2002 and 200.f require two successors
D. Because the late finish of 1001 and the late start of 7001 require two successors