The Development Team may need to learn or acquire new skills. Where is this list of skills found?
A. In the HR Training and Development Plan
B. As part of the outcome of the PI Planning pre-meeting
C. In the Improvement Roadmap
D. As part of the outcome of the Team Retrospective
正解:D
質問 # 58
Agile Release Trains are organized around the ability to release value on demand through the ________________________________.
質問 # 59
What activity calls for using ROAM technique?
A. Managing the ART sync.
B. Refining the Program Backlog.
C. Managing teams by the Release Train Engineer.
D. Categorizing program risks during PI Planning.
正解:D
質問 # 60
According to SAFe, which of the following metrics are reported at the Inspect and Adapt event?
A. Cumulative value measure
B. ART predictability measure
C. ART cycle velocity
D. Cumulative value rate
正解:B
解説:
According to the SAFe 6 Scrum Master documentation, one of the metrics that are reported at the Inspect and Adapt event is the ART predictability measure. This metric shows how well the ART delivers on its PI objectives, which are the SMART commitments made by the teams during PI planning. The ART predictability measure is calculated by dividing the total actual business value achieved by the total planned business value, as shown in the PI system demo. The ART predictability measure helps the ART to assess its performance, identify gaps, and improve its forecasting accuracy and reliability. (Must be taken from SAFe 6 Scrum Master resources) Reference:
Inspect and Adapt
Program Increment
Exam Study Guide: SSM (6.0) - SAFe Scrum Master
質問 # 61
What are the responsibilities of a Business Owner? (Select 2)
A. Assign business value to Team Objectives during PI Planning.
B. Assign business value to Epics and Features.
C. Participate in Post-PI Planning and assist trains in adjusting ART PI plans as needed.