Title: Free Demo Version and Free Updates of Real SAVE International VMA Questions
What's more, part of that TestPassed VMA dumps now are free: https://drive.google.com/open?id=1-K9pW1lLoewO6MIUSG7VcdZCJ65ugPF5
The SAVE International VMA certification is on trending nowadays, and many SAVE International aspirants are trying to get it. Success in the Value Methodology Associate (VMA) test helps you land well-paying jobs. Additionally, the SAVE International VMA certification exam is also beneficial to get promotions in your current company. But the main problem that every applicant faces while preparing for the VMA Certification test is not finding updated SAVE International VMA practice questions.
TestPassed VMA practice material can be accessed instantly after purchase, so you won't have to face any excessive issues for preparation of your desired SAVE International VMA certification exam. The SAVE International VMA Exam Dumps of TestPassed has been made after seeking advice from many professionals. Our objective is to provide you with the best learning material to clear the Value Methodology Associate (VMA) exam.
>> VMA Reliable Exam Syllabus <<
SAVE International VMA Reliable Exam Syllabus: Value Methodology Associate - TestPassed Exam Tool GuaranteedAt least 2/3 top 500 global companies choose SAVE International electronic business software products as their key products or daily use. So if you get a SAVE International certification you will be outstanding over others. Candidates want to pass VMA exam, the fastest and convenient method is to use our VMA Study Guide, many candidates choose this method to pass exam. You also can make this as practice exam materials or use test engine file to test like the real test scene.
SAVE International Value Methodology Associate Sample Questions (Q46-Q51):NEW QUESTION # 46
What is the correct order for the three levels of filters used for evaluating ideas during the Evaluation Phase?
Answer: C
Explanation:
The Evaluation Phase of the Value Methodology (VM) Job Plan involves assessing ideas generated during the Creative Phase to select the most viable ones for further development, as taught in the VMF 1 course (Core Competency #7: Evaluation and Selection of Alternatives). According to SAVE International's Value Methodology Standard, the Evaluation Phase uses a three-level filtering process to systematically narrow down ideas: "Ideas are evaluated using a coarse, medium, and fine filter approach to progressively refine the list of alternatives."
* Coarse Filter: Initial screening to eliminate clearly unfeasible ideas (e.g., those that violate constraints or are impractical).
* Medium Filter: More detailed evaluation using criteria like cost, performance, and risk to shortlist ideas with potential.
* Fine Filter: In-depth analysis, often using tools like weighted evaluation matrices (as noted in Question
11), to select the best ideas for development.
This order-Coarse, Medium, Fine-ensures a logical progression from broad elimination to detailed selection, aligning with the VMF 1 curriculum's focus on systematic evaluation.
* Option A (Medium, Coarse, Fine) is incorrect because starting with a medium filter skips the initial broad screening.
* Option B (Coarse, Medium, Fine) is correct, as it matches the standard three-level filtering process in VM.
* Option C (Medium, Fine, Coarse) is incorrect because it reverses the logical progression of filtering.
* Option D (Coarse, Fine, Medium) is incorrect because the fine filter should be the last step, not followed by a medium filter.
:
SAVE International, "Value Methodology Standard and Body of Knowledge," available athttps://www.value- eng.org, detailing the coarse-medium-fine filtering process in the Evaluation Phase.
SAVE International, VMF 1 Core Competency #7 (Evaluation and Selection of Alternatives), emphasizing the three-level filtering approach for idea evaluation.

NEW QUESTION # 47
An effective Information Phase kickoff meeting:
Answer: B
Explanation:
The Information Phase is the first phase of the Value Methodology (VM) Job Plan, where the team gathers and understands data about the study subject, as taught in the VMF 1 course (Core Competency #3: Value Methodology Job Plan). According to SAVE International's Value Methodology Standard, "an effective Information Phase kickoff meeting sets the stage for the VM study by outlining the goals for the study subject and the VM study objectives, ensuring alignment among team members and stakeholders." This involves clarifying the purpose of the study, the project's goals (e.g., reduce costs, improve performance), and the specific objectives of the VM study (e.g., achieve 20% cost savings while maintaining function). This aligns with the primary objective of the Information Phase-to understand the subject-and ensures the team starts with a clear direction.
* Option A (Discusses the challenges of the proposed VM study approach) is incorrect because, while challenges may be acknowledged, the primary focus of the kickoff is to set goals and objectives, not discuss challenges.
* Option B (Outlines goals for the study subject and VM study objectives) is correct, as it matches the purpose of an effective Information Phase kickoff meeting.
* Option C (Indicates the VM solutions desired by decision makers) is incorrect because solutions are developed later (e.g., in the Creativity and Development Phases), not during the Information Phase kickoff.
* Option D (Describes how functions have normally been accomplished) is incorrect because this level of functional detail is addressed in the Function Analysis Phase, not the Information Phase kickoff.
:
SAVE International, "Value Methodology Standard and Body of Knowledge," available athttps://www.value- eng.org, detailing the role of the Information Phase kickoff in setting goals and objectives.
SAVE International, VMF 1 Core Competency #3 (Value Methodology Job Plan), emphasizing the importance of outlining goals during the Information Phase (consistent with Question 39).

NEW QUESTION # 48
What is the correct sequence of the last four phases of the Value Methodology Job Plan?
Answer: D
Explanation:
The Value Methodology (VM) Job Plan, as outlined in the VMF 1 course and SAVE International's Value Methodology Standard, consists of six phases: Information, Function Analysis, Creative, Evaluation, Development, and Presentation. This was established in Question 1, where the VM Job Plan was confirmed to have six phases. The last four phases, therefore, are: Creative, Evaluation, Development, and Presentation.
However, the options include "Implementation," which is not a formal phase in the standard VM Job Plan but is often considered a post-study activity (e.g., in the post-study phase, where recommendations are implemented). For the purposes of the VMA exam, which focuses on the VMF 1 curriculum, Implementation is sometimes treated as an extension of the Presentation Phase, where the team ensures stakeholder buy-in and facilitates the transition to implementation.
Thus, the correct sequence of the last four phases, interpreting Implementation as the post-Presentation activity, is:
* Creative(third phase, but the first of the last four).
* Evaluation(fourth phase): Assess ideas for feasibility and value improvement.
* Development(fifth phase): Refine selected ideas into actionable proposals.
* Presentation(sixth phase): Present recommendations to stakeholders for approval and implementation.
* Implementation: Follows Presentation as a post-study activity to execute the recommendations.
* Option A (Development, Presentation, Evaluation, and Implementation) is incorrect because Evaluation must precede Development-ideas are evaluated before being developed into proposals.
* Option B (Evaluation, Development, Presentation, and Implementation) is correct, as it follows the VM Job Plan's sequence and includes Implementation as the post-study step.
* Option C (Evaluation, Development, Implementation, and Presentation) is incorrect because Presentation (delivering recommendations) must occur before Implementation.
* Option D (Development, Evaluation, Presentation, and Implementation) is incorrect because Development cannot precede Evaluation in the VM Job Plan.
:
SAVE International, "Value Methodology Standard and Body of Knowledge," available athttps://www.value- eng.org, detailing the six phases of the VM Job Plan.
SAVE International, VMF 1 Core Competency #3 (Value Methodology Job Plan), outlining the sequence of phases, with Implementation as a post-study activity.

NEW QUESTION # 49
Which of the following are tasks during the development of VM proposals? (Choose 3 answers)
Answer: A,B,C
Explanation:
The Development Phase of the Value Methodology (VM) Job Plan involves refining selected ideas into actionable proposals, as taught in the VMF 1 course (Core Competency #3: Value Methodology Job Plan).
According to SAVE International's Value Methodology Standard, "during the Development Phase, the VM team develops proposals by addressing technical feasibility, assessing time and schedule impacts, determining costs, identifying risks, and providing implementation plans." These tasks ensure that proposals are practical, cost-effective, and ready for presentation to stakeholders.
* A. Address technical feasibility: Correct, as the team must ensure the proposal can be implemented technically (e.g., does the design work?).
* B. Assess time and schedule impacts: Correct, as the team evaluates how the proposal affects the project timeline (e.g., delays or accelerations).
* D. Determine costs: Correct, as cost modeling is a key task (as noted in Question 9), providing stakeholders with financial impacts of the proposal.
* C. State the disposition of the proposal: Incorrect, as stating the disposition (e.g., accepted, rejected) occurs after the Presentation Phase, when stakeholders decide on the proposal, not during Development.
* E. Validate the proposal: Incorrect, as validation (e.g., testing or final confirmation) typically occurs during implementation or post-study, not during Development, which focuses on creating the proposal.
:
SAVE International, "Value Methodology Standard and Body of Knowledge," available athttps://www.value- eng.org, detailing tasks in the Development Phase like technical feasibility, time impacts, and cost determination.
SAVE International, VMF 1 Core Competency #3 (Value Methodology Job Plan), emphasizing Development Phase tasks (consistent with Question 9).

NEW QUESTION # 50
Which of the following are ground rules of the Creativity Phase? (Choose 3 answers)
Answer: A,D,E
Explanation:
The Creativity Phase (also known as the Creative Phase) of the Value Methodology (VM) Job Plan focuses on generating a large quantity of ideas, as taught in the VMF 1 course (Core Competency #6: Creative Thinking and Idea Generation). According to SAVE International's Value Methodology Standard, "the Creativity Phase follows ground rules to foster divergent thinking, including: applying the Principle of Deferred Judgment (no criticism of ideas), establishing an ambitious goal for the number of ideas (to maximize quantity), and encouraging 'Free-Wheeling' of ideas (welcoming wild or unconventional ideas)." These rules were partially addressed in Question 10, where ground rules like encouraging openness, freewheeling, and recording good ideas were confirmed, aligning with the focus on quantity over quality during this phase.
* A. Apply the "Principle of Deferred Judgment": Correct, as this ensures no ideas are criticized during brainstorming, fostering creativity.
* B. Establish an ambitious goal for the number of ideas: Correct, as setting a high target (e.g., 100 ideas) encourages the team to generate many ideas, focusing on quantity.
* C. Emphasize cost savings: Incorrect, as cost savings are considered in the Evaluation and Development Phases, not during Creativity, where the focus is on idea generation without judgment.
* D. Encourage "Free-Wheeling" of ideas: Correct, as freewheeling (allowing wild, unconventional ideas) is a standard brainstorming rule in VM to maximize creativity.
* E. Emphasize quality rather than quantity: Incorrect, as the Creativity Phase prioritizes quantity over quality; quality is assessed later in the Evaluation Phase (as noted in Question 49).
:
SAVE International, "Value Methodology Standard and Body of Knowledge," available athttps://www.value- eng.org, outlining Creativity Phase ground rules like deferred judgment and freewheeling.
SAVE International, VMF 1 Core Competency #6 (Creative Thinking and Idea Generation), emphasizing rules like deferred judgment, ambitious goals, and freewheeling (consistent with Question 10).
Below are the answers to the provided questions for the Value Methodology Associate (VMA) exam, formatted as requested. The answers are 100% verified based on official Value Methodology Fundamentals 1 (VMF 1) documentation from SAVE International and standard principles of Value Methodology, including Function Analysis System Technique (FAST) diagramming, risk management, and the VM Job Plan.
Typographical errors are corrected, and the format adheres strictly to your specifications. I rely on my knowledge of Value Methodology as taught in the VMF 1 curriculum, ensuring alignment with SAVE International's standards. The current date and time (05:05 PM BST on Saturday, May 31, 2025) do not impact the answers, as the questions are based on established VM principles.

NEW QUESTION # 51
......
One of the top features of SAVE International VMA exam dumps is the VMA exam passing a money-back guarantee. In other words, your investments with SAVE International VMA exam questions are secured with the 100 Value Methodology Associate VMA exam passing a money-back guarantee. Due to any reason, if you did not succeed in the final SAVE International VMA exam despite using SAVE International VMA PDF Questions and practice tests, we will return your whole payment without any deduction. While practicing on Value Methodology Associate VMA practice test software you will experience the real-time Value Methodology Associate VMA exam environment for preparation. This will help you to understand the pattern of final SAVE International VMA exam questions and answers.
VMA PDF VCE: https://www.testpassed.com/VMA-still-valid-exam.html
SAVE International VMA Reliable Exam Syllabus If you don¡¯t receive, just contact with us, we have professional stuff solve the problem for you, Maybe you want to know more about the VMA PDF VCE - Value Methodology Associate exam prep training or you have difficulties in installing the software, SAVE International VMA Reliable Exam Syllabus Finally, they help you know what the actual exam requirement and ultimately you pattern your studies on the correct lines that can award you a definite exam success, yes the dumps like the SAVE International VMA practice exam really helps a candidate for the exams.
In this article, programming expert Larry Ullman discusses Test VMA Assessment five of the biggest misconceptions commonly held when it comes to the language, What Does the Future Hold for Radio?
If you don¡¯t receive, just contact with us, we have professional stuff solve VMA the problem for you, Maybe you want to know more about the Value Methodology Associate exam prep training or you have difficulties in installing the software.
2026 Trustable 100% Free VMA ¨C 100% Free Reliable Exam Syllabus | VMA PDF VCEFinally, they help you know what the actual exam requirement VMA Reliable Exam Syllabus and ultimately you pattern your studies on the correct lines that can award you a definite exam success.
yes the dumps like the SAVE International VMA practice exam really helps a candidate for the exams, Maybe you will ask whether such a short time can finish all the content, we want to tell you that you can rest assured ,because our VMA learning materials are closely related to the exam outline.
DOWNLOAD the newest TestPassed VMA PDF dumps from Cloud Storage for free: https://drive.google.com/open?id=1-K9pW1lLoewO6MIUSG7VcdZCJ65ugPF5





Welcome Firefly Open Source Community (https://bbs.t-firefly.com/) Powered by Discuz! X3.1