Firefly Open Source Community

Title: Want to Know Your Readiness for Medical Professional CCM Exam? Take Our Online P [Print This Page]

Author: jamesro383    Time: yesterday 09:53
Title: Want to Know Your Readiness for Medical Professional CCM Exam? Take Our Online P
Many exam candidates feel hampered by the shortage of effective CCM practice materials, and the thick books and similar materials causing burden for you. Serving as indispensable choices on your way of achieving success especially during this exam, more than 98 percent of candidates pass the exam with our CCM practice materials and all of former candidates made measurable advance and improvement. All CCM practice materials fall within the scope of this exam for your information. The content is written promptly and helpfully because we hired the most processional experts in this area to compile the CCM practice materials. Our CCM practice materials will be worthy of purchase, and you will get manifest improvement.
Due to extremely high competition, passing the Certified Case Manager Certification Exam (CCM) (CCM) exam is not easy; however, possible. You can use ExamcollectionPass products to pass the CCM exam on the first attempt. The Certified Case Manager Certification Exam (CCM) (CCM) practice exam gives you confidence and helps you understand the criteria of the testing authority and pass the Certified Case Manager Certification Exam (CCM) (CCM) exam on the first attempt. ExamcollectionPass CCM Questions have helped thousands of candidates to achieve their professional dreams.
>> New CCM Exam Objectives <<
2026 100% Free CCM ¨CAuthoritative 100% Free New Exam Objectives | Valid Certified Case Manager Certification Exam (CCM) Cram MaterialsOur CCM study materials cover three vertions, they can meet all your needs. You can choose differet versions according to your own needs. CCM PDF materilas is instant acess to downlod,if you like, it can be transformed into a paper version, you can put it into your bags. CCM Soft test engine and CCM oline test engine are also can be you choice, CCM online test engine using the online tool and it can also provide the record for your process, and CCM online test engine can practice online anytime. If you have the nees like this, just choose us.
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions (Q37-Q42):NEW QUESTION # 37
If defects are identified during the Tests on Completion, which one of the following options is not available to the Parties under the Contract?
Answer: D
Explanation:
Under FIDIC contracts, when defects are identified during Tests on Completion, the Engineer may still issue the Taking-Over Certificate if the defects do not materially affect the intended use (Option A). The Engineer can refuse acceptance until defects are rectified and tests repeated (Option B). The Employer can also request to take over the works (Option C).
However, Option D is not a standard contractual provision; the contract does not stipulate that the Party not liable for rectifying defects is entitled to payment for repeated tests. Typically, costs of repeated tests due to defects are borne by the liable party.
References:
FIDIC Red, Yellow, and Silver Books, Sub-Clause 10.1 and 10.3 - Taking Over and Tests on Completion FIDIC Contract Manager Study Guide, Module on Project Close-Out and Defects

NEW QUESTION # 38
If the Engineer is required to obtain the Employer's prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
Answer: B,C
Explanation:
Under the FIDIC Red Book 1999 Edition, the Engineer is generally responsible for issuing determinations on claims and contract matters. However, if the Particular Conditions require the Engineer to obtain the Employer's prior approval before issuing such determinations, the Engineer's options become limited if that approval is not granted.
* Option C (Issuing the determination to the Contractor in the form and with the content agreeable to the Employer, with a remark that it is the Employer's determination and not the Engineer's determination)is a practical approach often taken. The Engineer may issue the determination as directed or approved by the Employer but must clarify that it reflects the Employer's decision rather than the Engineer's independent determination.
* Option D (Informing the Contractor of their inability to issue the determination, due to lack of Employer's approval)aligns with transparency and procedural correctness. The Engineer should notify the Contractor if they cannot proceed with the determination, explaining the reason to avoid misunderstanding or delay.
* Option A (Remain silent and do nothing)isnot appropriate, as it may cause project delays and disputes.
* Option B (Referring the matter directly to the Dispute Adjudication Board)without a determination from the Engineer is not standard procedure under the 1999 edition. The Engineer's determination or failure to determine generally triggers the dispute resolution process, but referral is normally after due process, including issuing or attempting to issue a determination.
Hence,Options C and Dare the appropriate courses of action.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 3.5 - Determinations
FIDIC Red Book 1999 Edition, Particular Conditions (typical clauses on Engineer's authority) FIDIC Contract Manager Study Guide, Module on Claims and Dispute Resolution

NEW QUESTION # 39
Which one of the following documents constitutes a contract and is considered binding on both parties, when the Employer wants to award the Contract to the tenderer?
Answer: D

NEW QUESTION # 40
In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions] Choose all of the correct answers (multiple possibilities).
Answer: C,E
Explanation:
Comprehensive and Detailed Explanation:
Option B is correct: When instructed to implement a Variation promptly, the Contractor must commence work and keep detailed records for subsequent valuation and impact assessment.
Option D is correct: The Contractor is required to submit, within 28 days, a description, programme, and price proposal relating to the Variation as part of contract procedures.
Option A is incorrect: The Contractor generally must proceed promptly regardless of dispute about foreseeability but may reserve rights via notices.
Option C is incorrect: Safety cannot be compromised; the Contractor should not undertake hazardous work without mitigation.
Option E is incorrect: The Contractor is generally bound to start work upon instruction even if the price is not yet agreed.
References:
FIDIC Red and Yellow Books 2017 Editions, Sub-Clause 3.5 - Variation Procedure FIDIC Contract Manager Study Guide, Module on Variations and Change Management

NEW QUESTION # 41
You are teaching a group of early career professionals in the Contract Management department about the FIDIC 2017 Rainbow Suite of contract, and you are explaining about the intention of Delay Damages. Which one of the following statements is correct?
Answer: C
Explanation:
Delay Damages under FIDIC are primarily a pre-agreed measure to incentivize the Contractor to complete works on time rather than full compensation for all losses suffered. They simplify the process by avoiding the need for the Employer to prove actual losses.
Option A is incorrect; Delay Damages are generally not full compensation.
Option C is incorrect because Delay Damages remove the Employer's burden to prove actual loss.
Option B is the correct interpretation.
References:
FIDIC Red, Yellow, Silver Books 2017 Editions, Sub-Clause 8.7 - Delay Damages FIDIC Contract Manager Study Guide, Module on Delay Damages

NEW QUESTION # 42
......
In the major environment, people are facing more job pressure. So they want to get CCM certification rise above the common herd. How to choose valid and efficient CCM guide torrent should be the key topic most candidates may concern. So now, it is right, you come to us. Our company is famous for its high-quality in this field especially for CCM Certification exams. It has been accepted by thousands of candidates who practice our study materials for their exam.
Valid CCM Cram Materials: https://www.examcollectionpass.com/Medical-Professional/CCM-practice-exam-dumps.html
Medical Professional New CCM Exam Objectives With the lapse of the time, our company has grown stronger to stronger and we may now justifiably feel proud that our company has become the pacesetter in this field, Before you buy, you can enter ExamcollectionPass Valid CCM Cram Materials website to download the free part of the exam questions and answers as a trial, If you are interested in ExamcollectionPass, you can first free download part of ExamcollectionPass's Medical Professional certification CCM exam exercises and answers on the Internet as a try.
History of Cable Modems, Converts from host Practice CCM Test byte order to network byte order, With the lapse of the time, our company hasgrown stronger to stronger and we may now Valid CCM Cram Materials justifiably feel proud that our company has become the pacesetter in this field.
Pass Your Medical Professional CCM Exam with ConfidenceBefore you buy, you can enter ExamcollectionPass website to CCM Download the free part of the exam questions and answers as a trial, If you are interested in ExamcollectionPass, you can first free download part of ExamcollectionPass's Medical Professional certification CCM exam exercises and answers on the Internet as a try.
it- Why Our Medical Professional Exams Experts At Number #1 New CCM Braindumps For Customer's Choice, This is the result of our efforts and the best gift to the user.





Welcome Firefly Open Source Community (https://bbs.t-firefly.com/) Powered by Discuz! X3.1