AgilePM-Foundation受験準備 & AgilePM-Foundation問題集時間は、私たちAPMG-Internationalがすべて計画に追いついていて、それでもなお便利な事項を踏んでいる場合に特に重要です。先延ばしに苦しみ、学習プロセス中に散発的な時間を十分に活用できない場合は、AgilePM-Foundationトレーニング資料を選択する理想的な方法です。学習の楽しさを享受できるだけでなく、AgilePM-Foundation認定を正常に取得できることを保証できます。 AgilePM-Foundation試験問題に挑戦した後、AgilePM-Foundationガイド急流について完全に理解できます。 APMG-International Agile Project Management (AgilePM) Foundation Exam 認定 AgilePM-Foundation 試験問題 (Q117-Q122):質問 # 117
What role, ideally, should be independent of the outcome to be achieved in a Facilitated Wordshop?
A. Workshop Facilitator
B. Business Ambassador
C. Business Visionary
D. Business Analyst
正解:A
解説:
The role that should ideally be independent of the outcome to be achieved in a Facilitated Workshop is the Workshop Facilitator4. This role manages the processes and dynamics of the workshop and should remain neutral and impartial4.
質問 # 118
How should DSDM team measure progress?
A. Based on what has been delivered at the end of a Timebox.
B. Through an analysis of the Instrumental Success Factors.
C. Based on the completion of activities rather than the delivery of products
D. Through a project dashboard
正解:A
解説:
A DSDM team should measure progress: B. Based on what has been delivered at the end of a Timebox5.
質問 # 119
Why might the priority of a requirement in the Product Backlog differ from what might otherwise be shown?
A. Different budget
B. Different quality
C. Different timeframe
D. Different resources
正解:C
解説:
Comprehensive and Detailed 150 to 300 words Explanation From Exact Extract of Agile Project Management (paraphrased):
AgilePM's MoSCoW prioritization is always applied within a defined timeframe (e.g., a release or timebox). A requirement can be a Must Have for a specific delivery window while being a Should/Could when viewed across the whole product roadmap. Timeboxing, dependency considerations, and the need to deliver a coherent, usable increment by a certain date mean that priority is inherently time-contextual. While budget and resources influence overall planning, AgilePM fixes time and cost to provide predictability and flexes scope to protect quality; thus, the most legitimate driver for a requirement's priority to change is the timeframe to which MoSCoW is applied. As delivery horizons shift (e.g., near-term release vs. later release), the same requirement's priority may be re-appraised to ensure the Business Case and Product/Release Goals are met. Therefore, Different timeframe is the correct reason that explains variations in backlog priority.
質問 # 120
In what phase is it first established whether further investigation of the project is justified?
A. Feasibility
B. Foundations
C. Pre-Project
D. Evolutionary Development
正解:A
解説:
It is during the Feasibility phase that it is first established whether further investigation of the project is justified3. This phase aims to determine if the proposed project is likely to be feasible from both a technical and business perspective.
質問 # 121
What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?
A. Terms of Reference
B. Management Approach Definition
C. Delivery Plan
D. Foundation Summary
正解:B
解説:
The DSDM product that reflects the approach to the management of the project as a whole, considering how the project will be organized and planned from a management perspective, is the Management Approach Definition2. This product outlines the overall strategy for managing the project, including aspects such as roles, responsibilities, and processes, ensuring that the project is aligned with its objectives and can be delivered successfully2.