PRINCE2-Foundation PDF、PRINCE2-Foundation的中問題集当社は、教材を担当しています。 ShikenPASSが顧客に販売したすべての製品は、PRINCE2思いやりのあるアフターサービスをお楽しみいただけます。 インストール、操作などの学習資料に問題がある場合は、オンラインワーカーがメールをPRINCE2 7 Foundation written Exam受信した後、すぐに返信します。 私たちはトラブルを恐れていません。 PRINCE2-Foundationご質問やご提案をお待ちしております。 問題の解決にお役立てください。 PRINCE2 7 Foundation written Exam 認定 PRINCE2-Foundation 試験問題 (Q173-Q178):質問 # 173
What is the change authority role permitted to authorize?
A. Risks to the project
B. Changes to stage tolerance
C. Adjustments to the limits on the change budget
D. Changes to the project that do not exceed a defined budget
正解:D
解説:
The role of the change authority in PRINCE2 is to authorize changes within the project that do not exceed a predefined budget. This role is designated to ensure that any change proposals are evaluated and approved without exceeding the allocated budget for changes, thereby maintaining control over project costs and scope.References: PRINCE2 Foundation Manual
質問 # 174
What 15the purpose of the 'progress! practice?
A. To review whether the use of the products is likely to lead to the expected benefits
B. To control events that could have a positive or negative effect on project objectives
C. To define the roles and responsibilities for monitoring progress
D. To measure actual achievements against the planned time and cost targets for the project
正解:D
解説:
The purpose of the 'Progress' practice in PRINCE2 is to provide a mechanism to monitor and compare the actual project progress against the planned objectives, particularly in terms of time and cost. This monitoring helps in identifying any deviations from the plan and facilitates timely corrective actions to keep the project on track.References: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation
質問 # 175
Which role is responsible for appointing the senior user in a project that is independent from a program?
質問 # 176
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.
A. an external
B. a corporate
C. a temporary
D. a technical
正解:C
解説:
In PRINCE2, a project is defined as a temporary organization that is set up to deliver one or more business products according to an agreed Business Case. The temporary nature of projects highlights their finite and unique aspects, distinguishing them from regular, ongoing operations. References: PRINCE2 Foundation manual, PRINCE2 official resources
質問 # 177
Which is an objective of the Closing a Project process?
A. Check that all benefits are realized before closing a project
B. Assess any benefits that have already been realized
C. Prepare the plan for the next stage
D. Produce a Benefits Review Plan to identify what benefits are expected