Based on the available scope information and required accuracy, different cost estimated models or methodologies are utilized Which of the following statements is NOT true?
A. The Deterministic model is used when Class 5 through 3 estimated are required
B. The Parametric model is used when detailed quantities are not known
C. The Parametric model is used when Class 5 or Class 4 estimates are required
D. The Deterministic model is used when Class 3 through 1 estimates are required
答案:A
問題 #116
What is the cycle time?
A. 6 minutes
B. 14 minutes
C. 17 minutes
D. 5 minutes
答案:C
解題說明:
Understanding the Cycle Time:
* A cycle time includes all the operations needed for one complete lift:
* Sling Up: 5 minutes
* Hoist Up: 4 minutes
* Discharge: 3 minutes
* Clear Unload Area: 3 minutes
* Hoist Down: 2 minutes
Calculate Total Cycle Time:
* Cycle Time = 5 + 4 + 3 + 3 + 2 = 17 minutes.
Cross-Verification:
* Option A (5 minutes): Incorrect. Excludes operations.
* Option C (14 minutes): Incorrect. Underestimates.
* Option D (6 minutes): Incorrect. Miscalculation.
* Option B (17 minutes): Correct.
問題 #117
What project cost elements would NOT normally be reflected in the Activity 1000?
A. Materials used in the construction
B. Home office expenses
C. Job site quality control
D. CPM processing and updating
答案:B
解題說明:
Activity-specific costs in CPM schedules typically include direct expenses like materials (C), field-related overhead (D), and specific schedule management tasks (B).
Home office expenses are classified as indirect costs and are not associated with any specific activity within the project schedule. They are accounted for in broader financial statements rather than in the activity-based budget.
References: PSP Study Guide, Section 1.3.10 - Cost Estimate Development, explains how costs are categorized and assigned in schedules.
問題 #118
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
A. 15 days.
B. 10 days.
C. 0 days.
D. 5 days.
答案:C
解題說明:
Impact of Overrun:
* Drafting (Activity C) and manufacturing (Activity D) are critical path activities.
* A 5-day overrun in drafting consumes all available time for manufacturing.
* Therefore, manufacturing cannot be delayed without affecting the release of the product.
Verification with PSP Guidelines:
The PSP Study Guide specifies that critical path activities have zero float, so delays propagate directly to the project finish (Ref: PSP Study Guide, Chapter 2A: Critical Path and Float).
問題 #119
A good change management plan___________.
A. involves only the project controls team
B. is provided to stakeholders after it is created