During a program's definition phase, it is determined that the best approach for delivering the programs intended benefits is to supplement corporate resources with the procurement of specific products and services from external suppliers.
The program manager should use which of the following to determine and/or document the results of the program procurement planning activity?
A. Make of buy decisions, alternatives analyses approach to competition, and best mix of contract types
B. Make-or-buy decisions, proposal evaluation criteria contract management, and RFQs
C. RFPs. alternatives analyses, approach to competition, and requests for quotes (RFQs)
D. Requests for proposals (RFPs), proposal evaluation criteria, contract management and best mix of contract types
答案:D
問題 #114
A program manager has a multiple-project program that is scheduled to be completed by year's end. During the program delivery phases of the protects several mandatory changes are identified that would extend the program's completion date
What is the next step for the program manager?
A. Submit a change request to extend the program schedule
B. Apply resource leveling to ensure the program is completed on schedule
C. Update the schedule to reflect the extended completion date
D. Adjust working hours to ensure the program is completed on schedule
答案:A
問題 #115
A program will generate revenue for several years after it ends. The program manager and the operations manager, who are accountable for managing the benefits after program closure, are in disagreement. The operations manager is concerned that information necessary for managing the processes and benefits after program closure will be unavailable. The program manager expresses that managing the benefits after program closure is not within the scope and must be managed through the scope management plan.
What should the program sponsor do?
A. Direct the program manager to assess the impact of this change and follow the established change management process
B. Direct the operations manager to allocate the necessary resources to establish proper plans for accepting the benefits and processes after program closure.
C. Direct the operations manager to allocate a resource to the program to ensure that knowledge transfer and process development occur before closure
D. Direct the program manager to develop the necessary plans to ensure benefits can be transitioned and sustained after program closure.
答案:D
問題 #116
What is the PRIMARY reason for considering a physical ting topology for connecting outlying buildings?
A. It is an easier physical design to install.
B. It is the most compelling design for any network requirement.
C. It is the most cost effective design ten a campus network.
D. It provides a redundant cable path for disaster recovery.
答案:D
問題 #117
During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized the program manager was asked to transition the program into operations.
At this stage, what is expected during the post-review session organized by the program manager?