Which statement about the Directing a Project process is FALSE?
A. Supports the PRINCE2 principle of manage by exception
B. Covers the day-to-day activities of the Project Manager
C. Provides a mechanism for the Project Board to assure that there is continued business justification
D. Is triggered by a request to initiate a project
答案:B
問題 #40
How does the project board use the 'manage by stages' principle to control the project?
A. By approving the project management team
B. By reviewing project viability at defined intervals
C. By reviewing previous project closure documentation
D. By ensuring that the benefits are managed and controlled
問題 #41
Which is a responsibility of a Team Manager?
A. Reviewing the status of the stage
B. Setting Work Package tolerances
C. Ensuring delivery of products in the Managing Product Delivery process
D. Producing Highlight Reports for the Project Manager
答案:C
問題 #42
Which are benefits of using PRINCE2?
1. It removes the need for activity-based planning
2. It promotes learning and continuous improvement
3. It can be applied to any type of project
4. It defines specific leadership and other interpersonal skills required
A. 1 and 2
B. 2 and 3
C. 1 and 4
D. 3 and 4
答案:B
解題說明:
The benefits of using PRINCE2 include promoting learning and continuous improvement, and its ability to be applied to any type of project. PRINCE2 provides a flexible methodology that encourages iterative learning from both current and past projects while being adaptable to various industries and project sizes. References:
PRINCE27 Foundation Handbook and official training materials.
問題 #43
How should the "managing a stage boundary' process be used towards the end of a project's final delivery stage?
A. To review an issue received from a team manager
B. To plan the activities of the closing a project' process
C. To implement any exception plan requests from the project board
D. To create a benefits management approach for corporate, programme management or the customer
答案:B
解題說明:
The "Managing a Stage Boundary" process should be used towards the end of a project's final delivery stage to plan the activities of the "Closing a Project" process. This includes preparing for the closure of the project by confirming project deliverables, ensuring all project work is completed and approved, and planning the activities that will ensure the project is formally closed and reviewed.References: = PRINCE2 7 Foundation handbook and online resources