【General】 AACE-PSP Guide Torrent - AACE-PSP Exam Prep - AACE-PSP Pass Rate

Posted at yesterday 17:14      View:19 | Replies:0        Print      Only Author   [Copy Link] 1#
BONUS!!! Download part of VCEEngine AACE-PSP dumps for free: https://drive.google.com/open?id=1fdrhKx8V6itwA9WNxHBygfc3urKtynaQ
We always strictly claim for our AACE-PSP study materials must be the latest version, to keep our study materials up to date, we constantly review and revise them to be at par with the latest AACE International syllabus for AACE-PSP exam. This feature has been enjoyed by over 80,000 takes whose choose our study materials. The one who choose our study materials that consider our website as the top preparation material seller for AACE-PSP Study Materials, and inevitable to carry all candidates the finest knowledge on exam syllabus contents. Not only that, we will provide you a free update service within one year from the date of purchase, in order to keep up the changes in the exam so that every candidates who purchase our AACE-PSP study materials can pass the exam one time.
The AACE-PSP exam is a rigorous assessment that tests the knowledge and skills of professionals in the planning and scheduling field. AACE-PSP exam covers a wide range of topics, including schedule development and maintenance, schedule analysis and reporting, risk management, and resource management. It is designed to assess the ability of professionals to analyze data, develop effective schedules, and communicate effectively with project stakeholders.
To be eligible for the AACE-PSP Certification Exam, candidates must have a minimum of 4 years of professional experience in project planning and scheduling. They must also have a bachelor's degree or equivalent education in a related field. Once they meet these requirements, candidates can register for the exam and begin preparing for it.
100% Pass Quiz 2026 AACE International AACE-PSP: Accurate Planning & Scheduling Professional (PSP) Exam Reliable Test LabsThe page of our AACE-PSP simulating materials provides demo which are sample questions. The purpose of providing demo is to let customers understand our part of the topic and what is the form of our AACE-PSP study materials when it is opened. In our minds, these two things are that customers who care about the AACE-PSP Exam may be concerned about most. And you can click all three formats of our AACE-PSP exam dumps to see.
The AACE-PSP (Planning and Scheduling Professional) Certification Program is an internationally recognized certification offered by AACE International. It is one of the most widely recognized certifications for professionals seeking to work in project planning and scheduling. This program has gained widespread acceptance across various industries, including construction, oil and gas, mining, and many more.
AACE International Planning & Scheduling Professional (PSP) Exam Sample Questions (Q214-Q219):NEW QUESTION # 214
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
  • A. Not suitable for projects with long durations.
  • B. Accuracy is increased by inserting delaying events into the as-planned schedule.
  • C. Not suitable for complicated projects with multiple planned critical paths.
  • D. Less accurate as the analysis advances through the project.
Answer: B
Explanation:
* As-Planned vs. As-Built (APAB) Analysis:
A simple APAB compares the planned schedule to the actual schedule to identify deviations.
It does not involve inserting delaying events or re-forecasting the schedule, which makes it unsuitable for detailed analysis.
* Limitations of APAB:
Unsuitable for complex projects (A).
Inserting delays is not part of APAB (B).
Accuracy diminishes for long projects (C) or those requiring granular mid-project analyses (D).
* Conclusion: The correct answer is B, as inserting delays into the as-planned schedule is not a feature of simple APAB analysis.

NEW QUESTION # 215
Determine the correct formula and date for the late finish for Activity 2002.

  • A. LS.2003 - 1 day -> 10-06-01.
  • B. LS.2003 - 1 day -> 10-05-01.
  • C. LS.2003 + 1 day -> 10-07-01.
  • D. LS.2003 - 1 day -> 11.06.01.
Answer: B
Explanation:
* Activity Relationships:
Activity 2002 is directly succeeded by Activity 2003 in the schedule.
The late start (LS) of Activity 2003 determines the late finish (LF) of Activity 2002, adjusted by any lags or additional constraints.
* Late Finish Calculation Formula:
LF of 2002 = LS of 2003 - 1 day.
This accounts for the predecessor-successor logic and the sequence of activities.
* Date Calculation:
Late start of 2003 = 10-06-01.
Late finish of 2002 = 10-06-01 - 1 day = 10-05-01.
* Verification:
PSP guidelines emphasize that late finish values are derived by subtracting any relevant time constraints from the successor's late start (Ref: PSP Study Guide, Chapter 2A: Backward Pass Calculations)

NEW QUESTION # 216
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:

  • A. Predecessor is activity 5001, successor is activity 8001
  • B. Predecessor is activity 9001, successor is activity 9002
  • C. Predecessor is activity 4001, successor is activity 8001
  • D. Predecessor is activity 5001, successor is activity 8002
Answer: A

NEW QUESTION # 217
EBS is an acronym for:
  • A. Enterprise Breakdown Structure
  • B. Elongated Budget Synopsis
  • C. European Basic Schedule
  • D. Eventual Base Structure
Answer: A

NEW QUESTION # 218
Before the work begins, the contractor considers crashing the schedule. How much would the crashed general conditions have to be reduced to break even with the normal cost budget?

  • A. S1.772 per day
  • B. General conditions do not need to be reduced to break even
  • C. $1.223 per day
  • D. $195 per day
Answer: A

NEW QUESTION # 219
......
Latest AACE-PSP Test Simulator: https://www.vceengine.com/AACE-PSP-vce-test-engine.html
P.S. Free & New AACE-PSP dumps are available on Google Drive shared by VCEEngine: https://drive.google.com/open?id=1fdrhKx8V6itwA9WNxHBygfc3urKtynaQ
Reply

Use props Report

You need to log in before you can reply Login | Register

This forum Credits Rules

Quick Reply Back to top Back to list