Firefly Open Source Community

   Login   |   Register   |
New_Topic
Print Previous Topic Next Topic

[Hardware] CCM Reliable Test Price, CCM Mock Exam

139

Credits

0

Prestige

0

Contribution

registered members

Rank: 2

Credits
139

【Hardware】 CCM Reliable Test Price, CCM Mock Exam

Posted at yesterday 19:54      View:21 | Replies:0        Print      Only Author   [Copy Link] 1#
2026 Latest VCETorrent CCM PDF Dumps and CCM Exam Engine Free Share: https://drive.google.com/open?id=155X_ZQQf_e8CxG7yebuJ7NND8qO7Qkeg
The VCETorrent Certified Case Manager Certification Exam (CCM) (CCM) PDF dumps file is a collection of real, valid, and updated CCM practice questions that are also easy to install and use. The CCM PDF dumps file can be installed on a desktop computer, laptop, and even on your smartphone devices. Just download VCETorrent Certified Case Manager Certification Exam (CCM) in CCM PDF Questions on your desired device and start Medical Professional CCM exam dumps preparation today.
Many people would like to fall back on the most authoritative company no matter when they have any question about preparing for CCM exam. Our company is definitely one of the most authoritative companies in the international market for CCM exam. What's more, we will provide the most considerate after sale service for our customers in twenty four hours a day seven days a week, therefore, our company is really the best choice for you to buy the CCM Training Materials.
CCM Mock Exam - Cert CCM GuideDesktop Certified Case Manager Certification Exam (CCM) (CCM) practice test software is the first format available at VCETorrent. This format can be easily used on Windows PCs and laptops. The Certified Case Manager Certification Exam (CCM) (CCM) practice exam software works without an internet connection, with the exception of license verification. One of the excellent features of this Certified Case Manager Certification Exam (CCM) (CCM) desktop-based practice test software is that it includes multiple mock tests that have Medical Professional CCM practice questions identical to the actual exam, providing users with a chance to get Certified Case Manager Certification Exam (CCM) (CCM) real exam experience before even attempting it.
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions (Q63-Q68):NEW QUESTION # 63
You are the Contract Manager of the Employer's Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer's Requirements require that: "the Contractor design in accordance with international and national technical regulations, and standards, [etc.]".
For piling works, the Employer's Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for
200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer's Requirements.
In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m.
However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding.
The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.
As the Employer's Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.
In your "Notice of the Employer's Representative's determination", what is your determination for the Contractor?
  • A. The Contractor is entitled to both Claims.
  • B. The Contractor is entitled to the Claim for the additional flood wall based on Unforeseeable difficulties only.
  • C. The Contractor is not entitled to either of the Claims.
  • D. The Contractor is entitled to the Claim for additional costs in relation to the piling, based on errors in the Employer's Requirement only.
Answer: A
Explanation:
Both claims are valid under the Silver Book principles:
The error in the Employer's Requirements (typo in NTS-PW-01) leads to entitlement for additional piling costs.
The unforeseen hydrological data causing additional flood protection works qualify as unforeseeable physical conditions entitling the Contractor to compensation.
Hence, Option D is correct - the Contractor is entitled to both claims.
References:
FIDIC Silver Book 2017 Edition, Sub-Clause 4.1 (Employer's Requirements) and Sub-Clause 4.12 (Unforeseeable Physical Conditions) FIDIC Contract Manager Study Guide, Module on Claims and Employer's Requirements

NEW QUESTION # 64
Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?
  • A. True
  • B. False
Answer: A
Explanation:
This statement is true. The Silver Book (EPC/Turnkey contracts) usually involves lump-sum payment, but if part payment is based on quantity or work done, this must be explicitly provided for in the Particular Conditions to avoid ambiguity.
Such provisions ensure clarity on payment terms in line with project specifics.
References:
FIDIC Silver Book 1999 & 2017 Editions, Sub-Clause 14 - Payment Provisions FIDIC Contract Manager Study Guide, Module on Payment Procedures

NEW QUESTION # 65
Applying FIDIC Silver Book (edition 1999), which one of the following elements shallnotform part of the time Programme/revised programme?
  • A. Review periods under Sub-Clause 5.2.
  • B. The sequence and timing of inspections and tests.
  • C. The intended order of the works.
  • D. The remedial work (if any) instructed under Sub-Clause 7.6.
Answer: D
Explanation:
Comprehensive and Detailed Explanation:
According to the FIDIC Silver Book, 1999 Edition (The Conditions of Contract for EPC/Turnkey Projects), the Contractor is required under Sub-Clause 8.3 ("Programme") to submit a time programme that illustrates the sequence and timing of the works, including milestones and key events. The intended order of the works (Option A), sequence and timing of inspections and tests (Option B), and review periods (Option D) related to contract management processes such as approval of design or submissions (Sub-Clause 5.2) are integral to effective scheduling and coordination.
However,remedial work instructed under Sub-Clause 7.6, which concerns remedying defects or damage, is generally not part of the initial or revised programme. Instead, remedial works are typically handled as separate tasks or incorporated into specific defect liability or rectification schedules after the main programme has been executed. Such remedial works arise from defects liability obligations and do not belong to the original or revised time programme used to plan the main construction phases.
This distinction is important because the programme reflects planned works execution, whereas remedial work is reactive and may be scheduled separately under defects liability clauses or final project close-out arrangements.
References:
FIDIC Silver Book 1999 Edition, Clause 8.3 - Programme
FIDIC Silver Book 1999 Edition, Clause 7.6 - Remedial Work
FIDIC Contract Manager Study Guide, Module on Time and Delay Management

NEW QUESTION # 66
Which one of the following statements is correct regarding the Provisional Sum under the FIDIC Red, Yellow, and Silver Books (edition 1999)?
  • A. Each Provisional Sum shall not be used, in whole or in part, in accordance with instructions from the Engineer.
  • B. The Provisional Sum cannot be issued by instruction either by the Engineer (or Employer in case of FIDIC Silver Book).
  • C. The Contractor shall, when required by the Engineer, produce proof to substantiate how it has used the Provisional Sum.
Answer: C
Explanation:
Comprehensive and Detailed Explanation:
Option B is correct. Under FIDIC contracts, the Contractor must provide proof of how the Provisional Sum has been expended when requested by the Engineer. This ensures transparency and proper use of funds allocated as Provisional Sums.
Option A is incorrect; Provisional Sums are often used based on instructions from the Engineer or Employer.
Option C is incorrect because Provisional Sums are precisely intended to be used, in whole or in part, according to Engineer's or Employer's instructions.
References:
FIDIC Red, Yellow, and Silver Books 1999 Edition, Sub-Clause 13.2 - Provisional Sums FIDIC Contract Manager Study Guide, Module on Payment Procedures

NEW QUESTION # 67
In the FIDIC Silver Book (edition 1999), if the Employer has instructed the Contractor as per Sub-Clause 8.6 to provide a revised programme to stay within Time of Completion, the Employer can claim additional costs.
This only applies if the revised programme is still too slow to complete the Works within the Time for Completion. Is this statement true or false?
  • A. True
  • B. False
Answer: A
Explanation:
This statement is true. Under FIDIC Silver Book 1999, Sub-Clause 8.6, the Employer can instruct the Contractor to submit a revised programme to meet the contractual Time for Completion. If, after such instruction, the revised programme still shows the Works will not complete on time, the Employer may claim additional costs (such as delay damages or compensation) due to continued delay.
Thus, the Employer's right to claim additional costs is contingent on the revised programme not enabling timely completion.
References:
FIDIC Silver Book 1999 Edition, Sub-Clause 8.6 - Revised Programme
FIDIC Contract Manager Study Guide, Module on Claims and Delay Damages

NEW QUESTION # 68
......
The Certified Case Manager Certification Exam (CCM) certification exam is one of the top-rated career advancement CCM certifications in the market. This Certified Case Manager Certification Exam (CCM) certification exam has been inspiring candidates since its beginning. Over this long period, thousands of Certified Case Manager Certification Exam (CCM) exam candidates have passed their CCM Certification Exam and now they are doing jobs in the world's top brands.
CCM Mock Exam: https://www.vcetorrent.com/CCM-valid-vce-torrent.html
Medical Professional CCM Reliable Test Price Check out features of these formats, Every question or request about CCM pass torrent files, no matter how trivial it seems, is important to person who makes it, Medical Professional CCM Reliable Test Price Except of high passing rate, we are also famous for our good after-sale service, Medical Professional CCM Reliable Test Price Do you have found an effective way to study and practice it?
Transparent Firewall Issues, You wanna take CCM a break, you better bang some pots, Check out features of these formats, Every question or request about CCM pass torrent files, no matter how trivial it seems, is important to person who makes it.
Trust the best-selling CCM Cert Guide Reliable Test PriceExcept of high passing rate, we are also famous for our good after-sale service, CCM Valid Exam Test Do you have found an effective way to study and practice it, So during your formative process of preparation, we are willing be your side all the time.
2026 Latest VCETorrent CCM PDF Dumps and CCM Exam Engine Free Share: https://drive.google.com/open?id=155X_ZQQf_e8CxG7yebuJ7NND8qO7Qkeg
Reply

Use props Report

You need to log in before you can reply Login | Register

This forum Credits Rules

Quick Reply Back to top Back to list