【General】 Free PDF 2026 Medical Professional Professional Dumps CCM Torrent

Posted at yesterday 16:54      View:23 | Replies:0        Print      Only Author   [Copy Link] 1#
P.S. Free 2026 Medical Professional CCM dumps are available on Google Drive shared by ITdumpsfree: https://drive.google.com/open?id=1U-CTxxvxElQ80tZt0WpoEaKdiF58dY2j
ITdumpsfree's Medical Professional CCM Exam Training materials is no other sites in the world can match. Of course, this is not only the problem of quality, it goes without saying that our quality is certainly the best. More important is that ITdumpsfree's exam training materials is applicable to all the IT exam. So the website of ITdumpsfree can get the attention of a lot of candidates. They believe and rely on us. It is also embodied the strength of our ITdumpsfree site. The strength of ITdumpsfree is embodied in it. Our exam training materials could make you not help recommend to your friends after you buy it. Because it's really a great help to you.
No need to go after substandard CCM brain dumps for exam preparation that has no credibility. They just make you confused and waste your precious time and money. Compare our content with other competitors like Pass4sure's dumps, you will find a clear difference in CCM material. Most of the content there does not correspond with the latest syllabus content. It also does not provide you the best quality. Likewise the exam collection's brain dumps are not sufficient to address all exam preparation needs.
Accurate CCM Test & Associate CCM Level ExamThe three versions of our CCM practice braindumps have their own unique characteristics. The PDF version of CCM training materials is convenient for you to print, the software version of training guide can provide practice test for you and the online version is for you to read anywhere at any time. If you are hesitating about which version should you choose, you can download our CCM free demo first to get a firsthand experience before you make any decision.
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions (Q97-Q102):NEW QUESTION # 97
Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities)
  • A. Both 'Disagreement' and 'Dispute' are defined terms under the Conditions of Contract.
  • B. If a Party is dissatisfied with the determination and has given Notice of Dissatisfaction (NOD) to the other party within a strict 28-day time limit, a Dispute arises and either Party may proceed under Sub- Clause 21.4 to obtain a DAAB decision on it.
  • C. In case the Engineer refuses to issue a Performance Certificate or to issue one with a correct date under Sub-Clause 11.9, and the Contractor has disagreed with the requested entitlement or relief in connection with this refusal, Dispute shall be deemed to have arisen.
  • D. The Dispute must be submitted to the Dispute Avoidance and Adjudication Board (DAAB) within 42 days, otherwise the NOD is deemed to have lapsed and is no longer valid.
Answer: B,C
Explanation:
Option A is correct. Under Sub-Clause 11.9 (Performance Certificate) refusal or incorrect issuance by the Engineer, combined with disagreement by the Contractor, may cause a Dispute to arise.
Option B is correct. If a Party is dissatisfied with a determination, it must give a Notice of Dissatisfaction (NOD) within 28 days to escalate the matter to a Dispute, allowing either Party to refer it to the DAAB as per Sub-Clause 21.4.
Option C is incorrect. The contract does not specify a 42-day time limit for submission to DAAB after NOD; timelines vary by contract and stage.
Option D is incorrect. 'Disagreement' is not a formally defined term in FIDIC contracts, whereas 'Dispute' is.
References:
FIDIC Red, Yellow, Silver Books 2017 Edition, Sub-Clause 11.9 and Clause 21 - Claims, Disputes, and Adjudication FIDIC Contract Manager Study Guide, Module on Dispute Resolution

NEW QUESTION # 98
The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.
  • A. False
  • B. True
Answer: B
Explanation:
Under FIDIC Red Book (1999), the Value Engineering Clause requires the Contractor to notify the Engineer with full details and cost implications when proposing Value Engineering changes. The Engineer then follows the Variation procedure in Sub-Clause 3.5 to agree or determine the cost adjustment, which will be reflected in the Contract Price.
This ensures transparent handling of Value Engineering proposals and proper contractual adjustments.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 13.1 - Value Engineering
FIDIC Contract Manager Study Guide, Module on Variations and Value Engineering

NEW QUESTION # 99
Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then ... [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies)
  • A. The Engineer is deemed to have no objection to use the revised programme submitted by the Contractor, for the Works.
  • B. The Contractor cannot proceed in accordance with the Programme.
  • C. The Engineer shall be deemed to have given a Consent and the revised programme shall be the Programme.
  • D. The Contractor shall submit a Notice to the Engineer or the Employer reminding him to give its approval on the revised programme.
Answer: A
Explanation:
Comprehensive and Detailed Explanation:
According to the FIDIC 2017 editions (Red, Yellow, and Silver Books), when the Contractor submits a revised programme, the Engineer or Employer has a limited time (typically 14 days) to review and raise any Notice of Non-Compliance if the programme does not meet contract requirements (Sub-Clause 8.3 or equivalent). If no notice is issued within this period, the Engineer or Employer is deemed to have no objection to the revised programme.
This does not imply formal approval or consent, but the programme can be used for the execution and administration of the works in the absence of objections. This avoids unnecessary delay due to inaction.
Option D is correct as it captures this deemed "no objection" position.
Option B is incorrect as "deemed consent" is stronger than FIDIC provisions state; it is more correct to say
"no objection".
Option A is incorrect since the Contractor does not have to remind the Engineer or Employer for consent within this period.
Option C is incorrect because the Contractor may proceed if no non-compliance is notified.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 8.3 - Programme
FIDIC Yellow Book 2017 Edition, Sub-Clause 8.3 - Programme
FIDIC Silver Book 2017 Edition, Sub-Clause 8.3 - Programme
FIDIC Contract Manager Study Guide, Module on Time and Delay Management

NEW QUESTION # 100
Regarding the FIDIC Red Book (edition 1999): which two statements are true in respect of Building Information Modelling (BIM)?
Choose all of the correct answers (multiple possibilities).
  • A. BIM is one of the digital data technologies used in all aspects of project planning, investigation, design, construction and operation.
  • B. For construction or building projects involving BIM, many Sub-Clauses of FIDIC Red Book (edition
    2017) should be thoroughly reviewed when drafting the Particular Conditions.
  • C. BIM is not related to the improvement of quality, accuracy, delivery times and cost savings.
  • D. General Conditions of Contract require the use of BIM.
Answer: A,B
Explanation:
Option B is correct: BIM is indeed a digital data technology applicable throughout the project lifecycle.
Option D is correct: Use of BIM requires careful consideration of contract clauses and appropriate adjustments in Particular Conditions.
Option A is incorrect; the 1999 edition does not mandate BIM use.
Option C is false; BIM improves quality, accuracy, delivery times, and cost efficiency.
References:
FIDIC Red Book 1999 & 2017 Editions - BIM and Contract Amendments
FIDIC Contract Manager Study Guide, Module on BIM and Digital Technologies

NEW QUESTION # 101
You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017).
The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?
  • A. The Contractor submits a Value Engineering proposal regarding the lighting system for the operation rooms. The Engineer is positive about the proposal and tells the Contractor they need to look into it.
  • B. The Engineer requests a proposal regarding a change in type of windows and doors. The Contractor submitted the proposal accordingly to the Engineer. The Engineer instructs the Variation.
  • C. The Employer verbally instructs a change in the type of doors. The Engineer issued a Notice describing the required change and denying any costs for the Contractor.
  • D. The Engineer instructs a change in slopes of the access road to the intensive care unit to meet the Employer's Requirement. The Engineer does so with a Notice in accordance with Sub-Clause 3.5.
Answer: D
Explanation:
Comprehensive and Detailed Explanation:
Option B is correct: A Variation is a formal change to the Works instructed by the Engineer via a Notice (Sub- Clause 3.5). This includes changes to design or execution such as slopes on a road.
Option A is a proposal, not yet a Variation. Positive interest does not constitute a Variation.
Option C is partially correct but depends on formal instruction after proposal acceptance; the question specifies the Engineer instructs the Variation, but since it was a request for proposal first, the Variation instruction comes later. Without explicit instruction, this is not yet a Variation.
Option D is invalid as verbal instruction plus a Notice denying cost claims does not constitute a proper Variation.
References:
FIDIC Yellow Book 2017 Edition, Sub-Clause 3.5 - Variation Procedure
FIDIC Contract Manager Study Guide, Module on Variations and Change Management

NEW QUESTION # 102
......
Once you start to become diligent and persistent, you will be filled with enthusiasms. Nothing can defeat you as long as you are optimistic. We sincerely hope that our CCM study materials can become your new purpose. Our CCM Exam Questions can teach you much practical knowledge, which is beneficial to your career development. And with the CCM certification, you are bound to have a bighter future.
Accurate CCM Test: https://www.itdumpsfree.com/CCM-exam-passed.html
So after buying CCM latest test pdf, if you have any doubts about the Certified Case Manager Certification Exam (CCM) study training dumps or the examination, you can contact us by email or the Internet at any time you like, Medical Professional Dumps CCM Torrent We look forward to meeting you, In this way, it will save you much energy and CCM exam cost, Medical Professional Dumps CCM Torrent Create and take notes on any question.
Equipment and facilities can develop problems that can render CCM them less effective or inoperable altogether, Lab Exercise: Voice Port Configuration, So after buying CCM Latest Test Pdf, if you have any doubts about the Certified Case Manager Certification Exam (CCM) CCM Practice Exams study training dumps or the examination, you can contact us by email or the Internet at any time you like.
2026 Medical Professional CCM: Perfect Dumps Certified Case Manager Certification Exam (CCM) TorrentWe look forward to meeting you, In this way, it will save you much energy and CCM exam cost, Create and take notes on any question, Our CCM exam dumps are customizable based on the time and type of questions.
P.S. Free 2026 Medical Professional CCM dumps are available on Google Drive shared by ITdumpsfree: https://drive.google.com/open?id=1U-CTxxvxElQ80tZt0WpoEaKdiF58dY2j
Reply

Use props Report

You need to log in before you can reply Login | Register

This forum Credits Rules

Quick Reply Back to top Back to list