Firefly Open Source Community

   Login   |   Register   |
New_Topic
Print Previous Topic Next Topic

[General] Project-Management Practice Exam - Latest Project-Management Test Testking

132

Credits

0

Prestige

0

Contribution

registered members

Rank: 2

Credits
132

【General】 Project-Management Practice Exam - Latest Project-Management Test Testking

Posted at yesterday 22:49      View:7 | Replies:0        Print      Only Author   [Copy Link] 1#
DOWNLOAD the newest BraindumpsPrep Project-Management PDF dumps from Cloud Storage for free: https://drive.google.com/open?id=1kGjxdTCdCVtLeFVvvQfU3fHGe_6gwlsc
Just as I have just mentioned, almost all of our customers have passed the exam as well as getting the related certification easily with the help of our Project-Management exam torrent, we strongly believe that it is impossible for you to be the exception. So choosing our ARE 5.0 Project Management (PjM) Exam exam question actually means that you will have more opportunities to get promotion in the near future, at the same time, needless to say that you will get a raise in pay accompanied with the promotion. What’s more, when you have shown your talent with ARE 5.0 Project Management (PjM) Exam certification in relating field, naturally, you will have the chance to enlarge your friends circle with a lot of distinguished persons who may influence you career life profoundly. So why are you still hesitating for purchasing our Project-Management Guide Torrent? Your bright future is starting from here!
NCARB Project-Management Exam Syllabus Topics:
TopicDetails
Topic 1
  • Project Quality Control: This section of the exam measures skills of project managers and covers procedures for ensuring quality and maintaining the Standard of Care throughout the project. It focuses on applying regulatory requirements, reviewing documentation for quality, reducing risks and liabilities, and managing the design process to preserve its objectives
Topic 2
  • Contracts: This section of the exam measures the skills of project managers and covers the analysis of contracts that govern the relationships between architects, owners, contractors, and consultants. It highlights verifying adherence to agreements, interpreting key contractual elements, and ensuring consultant work is properly integrated into the project.
Topic 3
  • Project Execution: This section of the exam measures skills of architectural associates and covers the management of project execution through administrative procedures rather than design decisions. It addresses evaluating budgets, managing scope changes, preparing project documentation in line with delivery methods, and securing necessary approvals from relevant authorities.
Topic 4
  • Resource Management: This section of the exam measures the skills of project managers and covers how to determine the right team composition and manage time allocation for successful project delivery. It focuses on evaluating criteria for assembling teams and ensuring resources are properly managed to execute the project within agreed terms.
Topic 5
  • Project Work Planning: This section of the exam measures the skills of architectural associates and covers the development and communication of an effective project work plan. It emphasizes maintaining schedules, setting clear criteria for work planning, and ensuring consistent communication with stakeholders, including owners, contractors, consultants, and internal staff.

NCARB - Project-Management - ARE 5.0 Project Management (PjM) Exam Authoritative Practice ExamWeb-based software works without installation. ARE 5.0 Project Management (PjM) Exam exam practice test software works on all well-known browsers, including Chrome, Firefox, Safari, and Opera. Trust BraindumpsPrep - NCARB Project-Management exam preparation products and be prepared for the ARE 5.0 Project Management (PjM) Exam at your home. Preparing and testing yourself, again and again, can be nerve-wracking, so in this scenario, we provide a NCARB Project-Management PDF for exam preparation.
NCARB ARE 5.0 Project Management (PjM) Exam Sample Questions (Q48-Q53):NEW QUESTION # 48
In response to a request for qualifications for a prospective project, the architect assembles a project team of mechanical, electrical, plumbing, and fire protection engineers.
What is the project?
  • A. the renovation of a commercial office building
  • B. a research university campus master plan
  • C. a new school for grades K-12
  • D. seismic upgrades of a 1950s era hospital
Answer: C
Explanation:
K-12 schools typically require comprehensive MEPFP (Mechanical, Electrical, Plumbing, Fire Protection) engineering services due to their complex needs-such as HVAC systems, lighting, life safety, and code compliance. Other options may not require the full suite of these services at the proposal stage, particularly a master plan or focused seismic upgrades.
References:
NCARB ARE 5.0 Handbook - Consultant coordination by project type
Ballast ARE 5 Review Manual - K-12 school systems requirements

NEW QUESTION # 49
When is a change order required?
  • A. To approve contractor's payment request
  • B. To document changes in the scope of work that affect contract sum or time
  • C. To reject a contractor's submittal
  • D. To clarify ambiguous contract documents without affecting cost or schedule
Answer: B
Explanation:
A change order is a formal document modifying the contract scope, cost, or time. It is required when the owner requests changes or unforeseen conditions affect the work. Clarifications without impact do not require change orders but may be handled through interpretations or bulletins. Change orders must be documented and agreed upon by all parties to avoid disputes. This procedure is fundamental in ARE 5.0 PjM contract administration.

NEW QUESTION # 50
The main goals on a large project are ease of communication and commitment from the project team.
Which scheduling technique should be used?
  • A. Milestone chart
  • B. Interactive bar chart
  • C. Critical path method
Answer: B
Explanation:
Interactive bar charts are ideal for large projects where team commitment and communication are priorities.
Unlike a simple milestone chart or the more complex Critical Path Method (CPM), interactive bar charts provide a visual, time-based representation of tasks that facilitates easy understanding across disciplines.
When developed in a collaborative setting (such as pull-planning or in-person planning sessions), these charts help the project team see their roles, identify dependencies, and commit to deliverables.
The ARE 5.0 Handbook (Project Management division) describes interactive bar charts as excellent tools for collaborative environments where schedule visibility and team accountability are essential.
These charts promote communication across team members and are easier for non-technical stakeholders to interpret.
Reference: NCARB ARE 5.0 Handbook - PjM Content Area 3: Project Work Planning

NEW QUESTION # 51
Who is responsible for verifying the accuracy of the contractor's payment application?
  • A. Architect
  • B. Owner
  • C. Construction manager
  • D. Contractor's accountant
Answer: A
Explanation:
The architect reviews the contractor's payment applications to verify work progress aligns with the schedule of values and contract documents. The architect recommends payment amounts to the owner but does not release funds. This function protects owner interests and ensures proper contract administration, as emphasized in ARE 5.0 PjM.

NEW QUESTION # 52
During the preparation of the construction documents, it was noted that the survey inaccurately located the property line. Consequently, the parking layout had to be redesigned to fit within the corrected property boundary.
The architect's additional costs and associated delay are the responsibility of which one of the following parties?
  • A. Civil Engineer
  • B. Architect
  • C. Owner
  • D. Surveyor
Answer: C
Explanation:
According to AIA B101 §5.1, the owner is responsible for providing the site survey and other site-related documentation. If the survey is inaccurate and causes delays or extra services, the owner is responsible for costs incurred. The architect should submit a claim for additional services.
* Surveyors are contracted by the owner (not by the architect unless explicitly stated).
* The architect is not liable for incorrect information furnished by the owner.
* Reference: AIA B101 §5.1 and §3.6
* NCARB ARE 5.0 Handbook - PjM Content Area 2: Budget and Contracts
====================

NEW QUESTION # 53
......
Our Project-Management learning questions engage our working staff in understanding customers’ diverse and evolving expectations and incorporate that understanding into our strategies, thus you can 100% trust our Project-Management exam engine. And our professional Project-Management Study Materials determine the high pass rate. According to the research statistics, we can confidently tell that 99% candidates after using our products have passed the Project-Management exam.
Latest Project-Management Test Testking: https://www.briandumpsprep.com/Project-Management-prep-exam-braindumps.html
P.S. Free 2026 NCARB Project-Management dumps are available on Google Drive shared by BraindumpsPrep: https://drive.google.com/open?id=1kGjxdTCdCVtLeFVvvQfU3fHGe_6gwlsc
Reply

Use props Report

You need to log in before you can reply Login | Register

This forum Credits Rules

Quick Reply Back to top Back to list