【Hardware】 Pass Guaranteed Medical Professional - CCM Newest Latest Test Question

Posted at 11 hour before      View:3 | Replies:0        Print      Only Author   [Copy Link] 1#
BTW, DOWNLOAD part of ActualtestPDF CCM dumps from Cloud Storage: https://drive.google.com/open?id=1MqYoQDkIqUL_HDgj57i-zjmUwbyJ4q_R
Services like quick downloading within five minutes, convenient and safe payment channels made for your convenience. Even newbies will be tricky about this process on the CCM exam questions. Unlike product from stores, quick browse of our CCM preparation quiz can give you the professional impression wholly. So, they are both efficient in practicing and downloading process. We also have free demo of CCM training guide as freebies for your reference to make your purchase more effective.
If you want to CCM practice testing the product of ActualtestPDF, feel free to try a free demo and overcome your doubts. A full refund offer according to terms and conditions is also available if you don't clear the Medical Professional CCM Practice Test after using the Certified Case Manager Certification Exam (CCM) (CCM) exam product. Purchase ActualtestPDF best CCM study material today and get these stunning offers.
3 Formats of Medical Professional CCM Dumps that Suit your Study StyleTo do this you just need to enroll in the CCM test and put all your efforts and prepare well for the CCM exam. For the quick and complete CCM exam preparation you can trust real and updated CCM PDF Questions and practice tests which you can download from ActualtestPDF. We are quite confident that with Medical Professional CCM Exam Dumps you can not only prepare well but also pass the challenging CCM exam with flying colors.
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions (Q76-Q81):NEW QUESTION # 76
Through which two of the following documents may the Employer give information to the Contractor of a planned timetable of meetings such as management meetings, site meetings, technical meetings, and progress meetings?
Choose all of the correct answers (multiple possibilities).
  • A. Specification
  • B. General Conditions of Contract
  • C. Employer's Requirements
  • D. Special Conditions
Answer: C,D
Explanation:
The timetable for meetings is usually set out in the Special Conditions (Particular Conditions) and/or the Employer's Requirements, which define project-specific administrative and management arrangements.
Special Conditions customize the General Conditions to the project and often specify meeting schedules.
Employer's Requirements detail the Employer's expectations, including communication protocols and meeting timetables.
The General Conditions (Option A) are standard and do not include project-specific meeting schedules.
The Specification (Option B) mainly covers technical requirements, not administrative matters like meetings.
References:
FIDIC Red and Yellow Books 1999 and 2017 Editions, Special Conditions and Employer's Requirements Sections FIDIC Contract Manager Study Guide, Module on Communication and Reporting

NEW QUESTION # 77
Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?
Choose all of the correct answers (multiple possibilities)
  • A. The Engineer cannot sell or otherwise dispose any remaining items and reinstate the Site at the Contractor's Cost.
  • B. The Employer is entitled to the cost of reinstating, clearing the Site and disposal cost to the extent they exceed the money received from selling the remaining Contractor's items on the Site.
  • C. The Employer cannot reinstate and clear the Site and dispose the remaining Contractor's items on the Site if the Contractor fails, as this is the Contractor's obligation.
  • D. The Employer may sell or otherwise dispose any remaining items and reinstate the Site at the Contractor's Cost.
Answer: B,D
Explanation:
* Option Ais correct: The Employer may sell or dispose of any items left by the Contractor and reinstate the Site, recovering costs from the Contractor.
* Option Cis correct: The Employer is entitled to recover costs for clearing, reinstatement, and disposal exceeding proceeds from sale.
* Option Bis incorrect; the Engineer does not hold this authority, but the Employer does under the contract.
* Option Dis incorrect; if the Contractor fails to clear the Site, the Employer may take action to protect the Site.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 8.7 - Contractor's Use of Site
FIDIC Contract Manager Study Guide, Module on Contract Administration Procedures

NEW QUESTION # 78
Which one of the following statements regarding drafting contracts based on FIDIC Books is correct?
  • A. Amending clauses, supposedly in the interest of the Employer, immediately nullifies all the advantages of standardization, and almost invariably introduces conflicting or ambiguous requirements on the parties, and often causes mistrust between them.
  • B. The Form of Contract is chosen by the Contractor and imposed by him on the Employer, who tenders on that basis.
  • C. The FIDIC Books provide people who draft contracts with great examples on how to draft a good contract model. Furthermore, arrangements from Red, Yellow and Silver Books can be easily mixed to get a good fit for a specific project.
  • D. People who draft contracts should, when preparing a new contract, always start with the question:where do I want to lay the most risks between Employer and Contractor, and does the Employer has the budget to reward Contractors with a high risk apatite?
Answer: D
Explanation:
Option D is correct because contract drafting should strategically allocate risks between parties based on who can best manage them and the Employer's budget for risk and reward. Understanding risk appetite is key to tailoring FIDIC contracts appropriately.
Option A is exaggerated; while amendments can introduce issues, careful drafting can preserve benefits of standardization.
Option B is partly true but mixing arrangements is complex and not always straightforward.
Option C is incorrect; the Employer usually chooses the contract form.
References:
FIDIC Contract Management Guidelines - Golden Principles
FIDIC Contract Manager Study Guide, Module on Contract Drafting and Risk Allocation

NEW QUESTION # 79
Under the FIDIC Red, Yellow, and Silver Books (edition 2017), if a Dispute is referred to the Dispute Avoidance and Adjudication Board (DAAB) to obtain its decision, the Parties shall suspend performing their obligations in accordance with the Contract, until they receive further directions from the DAAB. Is this statement true or false?
  • A. True
  • B. False
Answer: B
Explanation:
The statement is false. Under FIDIC 2017 editions, the referral of a dispute to the DAAB does not automatically suspend the Parties' contractual obligations. The works and contract performance generally continue while the dispute is adjudicated, unless otherwise agreed or ordered.
Suspension of obligations can disrupt project progress and is not encouraged by FIDIC procedures, which emphasize dispute resolution without delaying the work.
References:
FIDIC Red, Yellow, and Silver Books 2017 Edition, Clause 21 - Disputes and Adjudication FIDIC Contract Manager Study Guide, Module on Dispute Resolution

NEW QUESTION # 80
A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months.
This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?
  • A. In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.
  • B. The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.
  • C. If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.
  • D. If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.
Answer: A
Explanation:
Comprehensive and Detailed Explanation:
Option C is not true because under the FIDIC Silver Book (1999 edition), the delay damages (liquidated damages) specified in the contract are intended as full compensation for the Employer's loss resulting from late completion. The contract usually excludes other claims for actual losses or extra costs beyond the delay damages.
Option A is true; Variations can include extensions of time.
Option B is true; identifying delay causes is essential for claims and defences.
Option D is true; if the Employer causes suspension not attributable to the Contractor, delay damages claims by the Employer are generally unjustified.
Thus, the Employer cannot claim extra costs over and above delay damages as per typical Silver Book provisions.
References:
FIDIC Silver Book 1999 Edition, Sub-Clause 8 - Time for Completion and Delay Damages FIDIC Silver Book 1999 Edition, Sub-Clause 2.5 - Employer's Claims FIDIC Contract Manager Study Guide, Module on Claims and Delay Damages

NEW QUESTION # 81
......
If you want the CCM certification to change your life and make it better, what are you waiting for? You should act quickly and make use of spare time of study or work to obtain a CCM certification and master one more skill. With the help of our CCM Exam Materials, you will find all of these desires are not dreams anymore. With the high pass rate as 98% to 100%, our CCM learning questions can help you get your certification with ease.
CCM Study Test: https://www.actualtestpdf.com/Medical-Professional/CCM-practice-exam-dumps.html
Medical Professional CCM Latest Test Question What unzipping software do you recommend, As we know, millions of candidates around the world are striving for their dreams who have been work assiduously, but the truth is what they need is not only their own great effort paying for exams, but most importantly, a high-quality CCM actual real questions which can contribute greatly to make progress, Medical Professional CCM Latest Test Question How do strategy and wisdom mean concerning being the winner in the exams?
The Find My Friends option allows you to turn off CCM the ability for the optional Find My Friends app to share the device's location with others, The Cartoon Network streams many of its shows to your computer CCM Exam Vce Free or, with free downloadable apps, to Android devices and to the iPad, iPhone, and iPod touch.
100% Pass 2026 Medical Professional High Hit-Rate CCM: Certified Case Manager Certification Exam (CCM) Latest Test QuestionWhat unzipping software do you recommend, As we know, millions CCM Valid Study Questions of candidates around the world are striving for their dreams who have been work assiduously, but the truth is whatthey need is not only their own great effort paying for exams, but most importantly, a high-quality CCM actual real questions which can contribute greatly to make progress.
How do strategy and wisdom mean concerning CCM Valid Study Questions being the winner in the exams, Our intimate service such as the free trial demo before purchased and the one-year free update service of our CCM after you have purchased both show our honest efforts to you.
As the saying goes, an inch of gold is an inch of time.
DOWNLOAD the newest ActualtestPDF CCM PDF dumps from Cloud Storage for free: https://drive.google.com/open?id=1MqYoQDkIqUL_HDgj57i-zjmUwbyJ4q_R
Reply

Use props Report

You need to log in before you can reply Login | Register

This forum Credits Rules

Quick Reply Back to top Back to list