Firefly Open Source Community

   Login   |   Register   |
New_Topic
Print Previous Topic Next Topic

Valid CCM Exam Questions - CCM Test Practice

135

Credits

0

Prestige

0

Contribution

registered members

Rank: 2

Credits
135

Valid CCM Exam Questions - CCM Test Practice

Posted at 2 hour before      View:2 | Replies:0        Print      Only Author   [Copy Link] 1#
2026 Latest Dumpexams CCM PDF Dumps and CCM Exam Engine Free Share: https://drive.google.com/open?id=1rKPVHPb9Fff-cG2cSy8ey3Nn-TEGEgc9
I know your time is very valuable. We guarantee that you can download our products CCM exam questions immediately after payment is successful. After your current page shows that the payment was successful, you can open your e-mail address. Our system will send you a link to use CCM Guide quiz within five to ten minutes. Then you can study with our CCM praparation materials right away.
If you study on our test engine, your preparation time of the CCM guide braindumps will be greatly shortened. Firstly, the important knowledge has been picked out by our professional experts. You just need to spend about twenty to thirty hours before taking the Real CCM Exam. In addition, the relevant knowledge will be easy to memorize. Learning our CCM study quiz can also be a pleasant process. The saved time can be used to go sightseeing or have a rest.
Updates To The Medical Professional CCM Exam Are Free For 1 yearYou can try our CCM study demo for free. There is no any personal information required from your side. The CCM complete study material contains comprehensive test information than the demo. So if you are interested with our CCM free demo then go for the CCM complete questions & answers. We will give you the best offer for the CCM practice dumps. 100% pass with CCM training dumps at first time is our guarantee.
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions (Q13-Q18):NEW QUESTION # 13
Which one of the following statements is NOT correct in respect of FIDIC Yellow Book (both editions)?
  • A. The Contract typically becomes legally effective when the Employer issues the Letter of Acceptance to the Contractor.
  • B. The Contractor provides plant and designs (except as otherwise specified) and executes the other works, all in accordance with the Contract, which includes its Proposal and the Employer's Requirements.
  • C. A disproportionate amount of risks is allocated to the Contractor under the General Conditions.
  • D. The General Conditions allocate the risks between the parties on a fair and equitable basis.
Answer: C
Explanation:
Option C is NOT correct. FIDIC Yellow Book General Conditions aim to allocate risks fairly and equitably between the Employer and Contractor. The contract balances risks according to who is best able to manage them. It does not impose a disproportionate risk burden on the Contractor.
Options A, B, and D are correct statements describing typical contract formation, risk allocation, and Contractor's design and execution responsibilities.
References:
FIDIC Yellow Book 1999 and 2017 Editions - Introduction and Risk Allocation Clauses FIDIC Contract Manager Study Guide, Module on Introduction to FIDIC Contracts

NEW QUESTION # 14
Under the FIDIC Silver Contract (edition 2017), which two of the answers provide for preconditions for certification and payment of the Interim Payment Certificate?
Choose all of the correct answers (multiple possibilities).
  • A. Receipt of a statement via a letter showing the amounts to which the Contractor considers itself to be entitled.
  • B. The appointment of the Contractor and receipt of the Advance Payment Guarantee, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 14.2.1.
  • C. The appointment of the Contractor's Representative and receipt of the Performance Security, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 4.2.1.
  • D. Receipt of a statement and supporting documents.
Answer: B,D
Explanation:
Comprehensive and Detailed Explanation:
Option A is correct: Certification and payment of interim payments are conditional on Employer's receipt of the Contractor's appointment and the Advance Payment Guarantee (Sub-Clause 14.2.1).
Option D is correct: Payment also requires receipt of the Contractor's statement supported by relevant documentation.
Option B alone is insufficient without supporting documents.
Option C relates to appointment and performance security but is not a stated precondition for payment certification.
References:
FIDIC Silver Book 2017 Edition, Sub-Clause 14.6 - Interim Payment Certificates FIDIC Contract Manager Study Guide, Module on Payment Procedures

NEW QUESTION # 15
Regarding the FIDIC Red Book (edition 1999), which two statements are true?
  • A. A notice and other communications may be delivered by hand, courier and mail. In each case with proof of receipt is required to qualify as legally valid.
  • B. Notices and other communications may be sent in hand written, type written, in print or through an electronic original transmission system.
  • C. In emergency situations notices can also be submitted verbally (rather than (also) in writing).
  • D. A notice is to be signed by the Engineer, Contractor's Representative or Employer's Authorised Representative.
Answer: B,C
Explanation:
Comprehensive and Detailed Explanation:
Option A is true: In emergencies, verbal notices are permitted with the requirement to follow up in writing.
Option D is true: Notices and communications may be sent in various formats including handwritten, typed, printed, or electronic systems.
Option B is incorrect; a notice does not necessarily have to be signed by all these representatives; it depends on the party issuing the notice.
Option C is incorrect; proof of receipt is ideal but not always strictly required for legal validity depending on contract provisions.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 1.3 - Communications and Notices FIDIC Contract Manager Study Guide, Module on Contract Communication

NEW QUESTION # 16
A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months.
This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?
  • A. If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.
  • B. If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.
  • C. In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.
  • D. The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.
Answer: C
Explanation:
Comprehensive and Detailed Explanation:
Option C is not true because under the FIDIC Silver Book (1999 edition), the delay damages (liquidated damages) specified in the contract are intended as full compensation for the Employer's loss resulting from late completion. The contract usually excludes other claims for actual losses or extra costs beyond the delay damages.
Option A is true; Variations can include extensions of time.
Option B is true; identifying delay causes is essential for claims and defences.
Option D is true; if the Employer causes suspension not attributable to the Contractor, delay damages claims by the Employer are generally unjustified.
Thus, the Employer cannot claim extra costs over and above delay damages as per typical Silver Book provisions.
References:
FIDIC Silver Book 1999 Edition, Sub-Clause 8 - Time for Completion and Delay Damages FIDIC Silver Book 1999 Edition, Sub-Clause 2.5 - Employer's Claims FIDIC Contract Manager Study Guide, Module on Claims and Delay Damages

NEW QUESTION # 17
The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition
1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract back- to-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions:
"Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer's Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause
5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer's Requirements, its items of reference or Contractor's design of the Works for the scope part for which Subcontractor is contracted." What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?
  • A. I would advise the SC not to enter this contract because the Contractor is obliged to act in accordance with good faith. A proposed paragraph like this opposes good faith.
  • B. I would advise the SC not to enter this contract, because Sub-Clause 4.4 describes the obligations of SC towards Contractor, but this amendment positions the SC in a vulnerable position for claims regarding all errors, faults or other Defects (whether originating from the Employer's Requirements or the design of the Contractor). Essentially, this means the SC becomes liable for the design part, which is within the scope of Contractor even without SC having the opportunity to review it.
  • C. I would advise the SC to enter the Contract with the request to the Contractor to delete this amendment in the Particular Conditions. If the Contractor does not agree to do so, at least the Subcontractor has tried its best.
  • D. I would advise the SC to discuss this amendment with the insurance company just to be sure there will be no transfer of risks. This amendment is mainly a consequence of the FIDIC Yellow Book structure, where the Contractor has obligations in terms of scrutinizing the Employer's Requirements. This amendment makes this obligation more explicit. If the insurance company has no problems with insuring the parts which will be delivered by SC to Contractor, the SC can accept this risk and enter into the subcontract.
Answer: B
Explanation:
In FIDIC Yellow Book (1999), the Contractor is responsible for scrutinizing the Employer's Requirements per Sub-Clause 5.1 and must notify any discrepancies or errors. However, passing this obligation to a Subcontractor, and requiring the Subcontractor to indemnify the Contractor for errors or defects arising from the Employer's Requirements or the Contractor's design, unfairly shifts risk and liability to the Subcontractor.
The Subcontractor is likely not in a position to fully review or control the Employer's Requirements or the overall Contractor's design. This exposes the Subcontractor to excessive risk, beyond their scope and capacity.
Advice C highlights that the Subcontractor becomes vulnerable to claims for design defects outside their control. This misallocation of risk is generally not recommended and can be challenged during contract negotiation. Good contract management practice and risk allocation principles (FIDIC Contract Manager Study Guide, Module on Claims and Dispute Resolution) support this position.
While Options A, B, and D propose different approaches, only C correctly identifies the fundamental contractual and risk management issue that should prevent the Subcontractor from entering the contract as is.
References:
FIDIC Yellow Book 1999, Sub-Clause 5.1 - Contractor's General Obligations FIDIC Contract Manager Study Guide, Module on Claims and Dispute Resolution FIDIC Contract Manager Study Guide, Module on Risk Management

NEW QUESTION # 18
......
After paying our CCM exam torrent successfully, buyers will receive the mails sent by our system in 5-10 minutes. Then candidates can open the links to log in and use our CCM test torrent to learn immediately. Because the time is of paramount importance to the examinee, everyone hope they can learn efficiently. So candidates can use our CCM Guide questions immediately after their purchase is the great advantage of our product. It is convenient for candidates to master our CCM test torrent and better prepare for the CCM exam.
CCM Test Practice: https://www.dumpexams.com/CCM-real-answers.html
So, we're sure it absolutely can help you pass CCM exam and get Medical Professional certificate and you don't need to spend much time and energy on preparing for CCM exam, Medical Professional Valid CCM Exam Questions Even if you fail the exam, we will give back your money or you can choose to change other exam materials for free, If you get lost in so many choice for your CCM exam test, please keep clam and pay attention to our valid study material.
The first category requires candidates to pass a certain exam, whereas, CCM in the second category, candidates are assessed when they are working either alone or in groups, followed by interview from exam assessors.
New Launch CCM PDF Dumps [2026] - Medical Professional CCM Exam QuestionIt would have taken us weeks to try to get an unfamiliar CCM Test Practice tool working, and we didn't want to pay for a tool without knowing it would work, So, we're sure itabsolutely can help you Pass CCM Exam and get Medical Professional certificate and you don't need to spend much time and energy on preparing for CCM exam.
Even if you fail the exam, we will give back New CCM Test Tutorial your money or you can choose to change other exam materials for free, If you get lost in so many choice for your CCM exam test, please keep clam and pay attention to our valid study material.
Please remember to check mailbox and practice them regularly, which is also of great use to your exam connected with Medical Professional Exams CCM study vce, and this kind behavior is totally free as our little gift for you.
However if you buy our CCM exam engine, you just only need to spend 20-30 hours to practice training material and then you can feel secure to participate in this exam.
P.S. Free 2026 Medical Professional CCM dumps are available on Google Drive shared by Dumpexams: https://drive.google.com/open?id=1rKPVHPb9Fff-cG2cSy8ey3Nn-TEGEgc9
Reply

Use props Report

You need to log in before you can reply Login | Register

This forum Credits Rules

Quick Reply Back to top Back to list