【General】 CMAA Construction-Manager Accurate Study Material & Construction-Manager Exa

Posted at yesterday 01:55      View:15 | Replies:0        Print      Only Author   [Copy Link] 1#
BTW, DOWNLOAD part of PassTestking Construction-Manager dumps from Cloud Storage: https://drive.google.com/open?id=1GxH5loE8C4IDfHZPr8vua8RjzzIpS22e
The client can try out and download our Construction-Manager training materials freely before their purchase so as to have an understanding of our Construction-Manager exam questions and then decide whether to buy them or not. The website pages of our product provide the details of our Construction-Manager learning questions. You can see the demos of our Construction-Manager Study Guide, which are part of the all titles selected from the test bank and the forms of the questions and answers and know the form of our software on the website pages of our Construction-Manager study materials.
AS is known to all of us, no pain, no gain. It's also applied in a Construction-Manager exam, if we want to pass the Construction-Manager exam, you also need to pay the time, money as well as efforts. However, induction may be quite difficult for someone who have little time to preparing the Construction-Manager exam. If you face the same problem like this, our product will be your best choice, the practice materials will provide you the most excellent and best ways for the exam. Our product for the Construction-Manager Exam will help you to save the time as well as grasp the main knoeledge point of the Construction-Manager exam.
Construction-Manager Exam Review & Valid Construction-Manager Study GuideLife is full of choices. Selection does not necessarily bring you happiness, but to give you absolute opportunity. Once missed selection can only regret. PassTestking's CMAA Construction-Manager exam training materials are necessary to every IT person. With this materials, all of the problems about the CMAA Construction-Manager will be solved. PassTestking's CMAA Construction-Manager exam training materials have wide coverage, and update speed. This is the most comprehensive training materials. With it, all the IT certifications need not fear, because you will pass the exam.
CMAA Certified Construction Manager (CCM) Sample Questions (Q31-Q36):NEW QUESTION # 31
What are the essential components of the Risk Management process?
  • A. Avoiding, tracking, mitigation, transferring
  • B. Communicating and reporting, assessing, mitigation, tracking
  • C. Avoiding, mitigating, transferring, accepting
  • D. Communicating and reporting, tracking, mitigation, resolution
Answer: C
Explanation:
According to theCMAA Construction Management Standards of Practice, Chapter 10 - Risk Management, the fundamental components of the risk management process include:
Avoidance- Eliminating the risk entirely by altering plans or scope.
Mitigation- Reducing the likelihood or impact of a risk.
Transfer- Shifting risk responsibility to another party, typically through insurance or contracts.
Acceptance- Recognizing the risk and planning to manage its consequences.
CMAA defines risk management as:
"A systematic process of identifying, analyzing, responding to, and monitoring risks to minimize their impact on project objectives." These four response strategies-avoid, mitigate, transfer, and accept-are universally recognized as the essential framework for construction risk management.
References:
CMAA Construction Management Standards of Practice, Chapter 10 - Risk Management, Section: "Risk Identification and Response," pp. 96-99.
CMAA CM Study Guide, Risk Management Domain, Objective 10.3: "Develop and apply risk response strategies: avoid, mitigate, transfer, and accept."

NEW QUESTION # 32
ACM agent has assisted the owner by creating contractual safety requirements. By reviewing the contractor's safety submittals, the CM
  • A. accepts responsibility and liability for site safety.
  • B. certifies that the submittals cover all site conditions that may occur.
  • C. approves the contractors fall protection program.
  • D. determines if the contract specifications have been met.
Answer: D
Explanation:
TheCMAA Standards of Practice, Chapter 7 - Safety Managementstates that the Construction Manager's role in reviewing safety submittals islimited to ensuring that the contractor's safety program complies with the contractual and regulatory requirements, not to certify or approve safety programs.
CMAA clarifies:
"The Construction Manager's review of safety submittals is for the purpose of verifying that the contractor's plan meets the requirements set forth in the contract documents. The CM does not assume or accept responsibility for site safety." Therefore, the CM's duty isreview and determination of contractual compliance, not approval or certification, and certainly not assumption of liability.
References:
CMAA Construction Management Standards of Practice, Chapter 7 - Safety Management, Section:
"Contractor's Safety Responsibilities," pp. 69-71.
CMAA CM Study Guide, Safety Management Domain, Objective 7.3: "Review contractor's safety plans for compliance with contract requirements."

NEW QUESTION # 33
During the design phase, the CM should perform which of the following tasks?
  • A. Review staffing assignments, labor affidavits, and historical trust.
  • B. Review plans, final Right-of-Way (ROW) documents, and as-built submittals.
  • C. Review contract milestones, payment procedures, and communication procedures.
  • D. Review cost estimate, schematic design, and scheduling conferences with regulatory agencies.
Answer: D
Explanation:
In theCMAA Project Managementchapter, during theDesign Phase, the CM's duties focus on evaluatingdesign progress, cost control, and schedule integration.
The CMAA SOP specifies:
"During the design phase, the Construction Manager should review design submissions for compliance with budget, schedule, and program requirements; participate in cost estimating and design coordination meetings; and support permitting and regulatory agency coordination." OptionBcorrectly reflects these core design-phase responsibilities: reviewing cost estimates, schematic design development, and attending scheduling or coordination conferences with agencies.
The other options refer to administrative, construction-phase, or post-construction tasks, not design-phase CM functions.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 2 - Project Management, Section: "Design Phase Services," pp. 23-26.
CMAA Study Guide, Project Management Domain, Objective 2.3.

NEW QUESTION # 34
An agency CM is overseeing the construction of a large, complex multi-story, high security building in a remote area. The building had a specialized spire installed at the top, which serves as an encrypted signal transmitter. Construction is complete and the contractor has de-mobilized, but then it is discovered that the signal transmitter is not transmitting the signal. The owner's QC plan required testing for the functionality of the transmitter, but the contractor has not shown test results reflecting adequate performance. Who is responsible for the cost of remobilization?
  • A. Agency CM
  • B. Contractor
  • C. Owner
  • D. Designer of record
Answer: B
Explanation:
In CMAA's Standards of Practice underContract AdministrationandQuality Management, the contractor is contractually obligated to perform all required tests and deliverables, as defined in the contract documents (including the owner's QC plan). If a required test (such as functional performance testing of a specialized transmitter) fails to meet contractual requirements or is not documented, the risk and cost of ensuring compliance (including remobilization) generally rests with the contractor, unless the contract allocates it differently.
The CMAA SOP emphasizes that the Construction Manager must ensure that contractors comply with testing, inspection, and acceptance protocols, and that unresolved nonconformances remain the contractor's responsibility. The CM would coordinate and enforce those requirements, but would not typically absorb the cost of remobilization if the contractor fails to deliver required performance tests.
Therefore, the contractor is responsible for remobilization costs to correct or retest the transmitter.

NEW QUESTION # 35
Who owns the float in a typical project critical path schedule?
  • A. Construction manager
  • B. Contractor
  • C. Owner
  • D. Project
Answer: D
Explanation:
According toCMAA Time Managementstandards,floatis defined as the amount of time an activity can be delayed without affecting the overall project completion date. The SOP specifies:
"Float is a shared resource belonging to the project as a whole. It is not owned exclusively by any single party
- owner, contractor, or construction manager."
This principle ensures fair schedule management and prevents disputes. Both the CM and the contractor should work collaboratively to optimize float use for the benefit of the entire project. Contract documents (e.
g., general conditions) may further define float management policies, but unless specified otherwise, float is treated asa project resource, not the property of any one participant.
Therefore, the correct answer isC. Project.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Time Management, Section: "Float Ownership." CMAA CM Study Guide, Time Management Domain, Objective 5.3: "Manage schedule float as a shared project resource."

NEW QUESTION # 36
......
Many candidates are interested in our software test engine of Construction-Manager. This version is software. If you download and install on your personal computer online, you can copy to any other electronic products and use offline. The software test engine of Construction-Manager is very practical. It can be used on Phone, Ipad and so on. You can study any time anywhere you want. Comparing to PDF version, the software test engine of CMAA Construction-Manager also can simulate the real exam scene so that you can overcome your bad mood for the real exam and attend exam casually.
Construction-Manager Exam Review: https://www.passtestking.com/CMAA/Construction-Manager-practice-exam-dumps.html
It is also known to us that passing the exam is not an easy thing for many people, so a good study method is very important for a lot of people, in addition, a suitable study tool is equally important, because the good and suitable Construction-Manager reference guide can help people pass the exam in a relaxed state, We are a responsible company concentrating on the profession of the Construction-Manager exam bootcamp and after-sales services for over ten years.
Search Options in SharePoint Server, Universal Domain membership is Construction-Manager in the Global Catalog, It is also known to us that passing the exam is not an easy thing for many people, so a good study method is very important for a lot of people, in addition, a suitable study tool is equally important, because the good and suitable Construction-Manager reference guide can help people pass the exam in a relaxed state.
Construction-Manager Accurate Study Material - 2026 CMAA Certified Construction Manager (CCM) Realistic Exam Review Pass GuaranteedWe are a responsible company concentrating on the profession of the Construction-Manager exam bootcamp and after-sales services for over ten years, All the Construction-Manager latest vce content are the same and valid for different formats.
But if you failed the exam with our Construction-Manager free dumps, we promise you full refund, From the Construction-Manager dumps free you will find the difference between us and the others.
BONUS!!! Download part of PassTestking Construction-Manager dumps for free: https://drive.google.com/open?id=1GxH5loE8C4IDfHZPr8vua8RjzzIpS22e
Reply

Use props Report

You need to log in before you can reply Login | Register

This forum Credits Rules

Quick Reply Back to top Back to list